Free sample paper for MT381 Unit 7
Ten Electricians and Two Telehandlers: An MT381 Unit 7 Resource-Leveled Schedule and the Float It Spends
[Student Name]
Purdue University Global
MT381: Construction Planning and Scheduling
Unit 7 Resource-Leveled Schedule
[Instructor Name]
[Date]
The crews, limits and results are composite; the leveling was computed with the stated script, and the sources cited are real.
The Two Resources
Electricians are assigned by activity: six for overhead rough-in and six for in-wall rough-in on each level, two for trim-out on each level and four for setting and terminating the switchgear. The electrical subcontractor has committed ten electricians to the job. Telehandlers are limited to two by the staging area on the north side of the site; framing, curtain wall and roofing each need one, and brick veneer needs two for its scaffold and pallets.
The Early-Date Histogram
Plotted from early dates, electrician demand overlaps in two places. From July 15 to July 28, level 1 in-wall rough-in runs alongside level 2 overhead rough-in; from July 29 to August 11, level 2 in-wall rough-in runs alongside level 3 overhead rough-in. Each overlap puts twelve electricians on the job, two more than committed, on twenty working days in all. Telehandler demand peaks at four, from July 19 through the rest of July, when framing, roofing and brick all run together, and exceeds two on 31 working days through September 3.
Why the Peak Matters to the Subcontractor
A peak of twelve for four weeks is not just a number above a line. To meet it, the electrical subcontractor would have to pull two electricians from another job, hire them for a month or work the existing crew overtime, and each choice has a cost. Mubarak (2015) points out that a crew that swells and shrinks repeatedly costs more than a steady one, through hiring, orientation and lost learning, which is why contractors prefer histograms that rise and fall gradually even when the total hours are the same. The commitment of ten reflects what the subcontractor can staff without disrupting its other work.
The Leveling Script
The script uses a serial method. It considers activities in order of their late start, so the activities with the least room to move are placed first, and it schedules each one at the earliest date its logic allows on which its crew fits under the limit for every day of its duration. Hegazy (1999) describes leveling as a trade-off between resource limits and project duration that heuristic and optimization methods approach differently; the serial late-start rule is a common heuristic and is transparent enough to check by hand.
Three Runs
Run one, unlimited, reproduces the early dates and the December 15 finish.
Run two caps electricians at ten. Rough-in on each level must take turns. The four-activity level 2 rough-in chain, from overhead work to the cover inspection, slides ten working days, starting July 29 instead of July 15. The level 3 rough-in chain slides twenty, starting August 26 instead of July 29. The histogram never rises above ten. Completion holds on December 15, because both chains had enough float: the level 2 chain keeps 19 of its 29 days and the level 3 chain keeps 11 of its 31.
Run three caps electricians at ten but allows twelve from July 20 through August 24. The rough-in chains on levels 2 and 3 slide only three days, waiting for the window to open, and then run as planned. Two additional electricians are needed on 17 working days, from July 20 to August 16. The level 2 chain keeps 26 days of float and the level 3 chain keeps 28. Completion again holds on December 15.
Every run finishes on December 15; what differs is how much margin the job keeps for the problems it has not met yet.
Telehandlers in the Same Pass
Telehandlers are leveled in the same pass with a limit of two. Framing and roofing keep their dates because they are ahead in priority, and brick veneer, which needs both machines, slides 36 standard working days later, starting September 8 instead of July 19 and finishing October 28. Brick had 48 days of total float, so 12 remain. Paving and landscaping, which follow the brick, slide with it, leaving paving 11 days and landscaping 13. Completion is unaffected.
What Leveling Spent
Float consumed by leveling is listed activity by activity, because it is no longer available to absorb a late delivery or a bad week of weather. In run two, the level 3 rough-in chain falls from 31 days to 11, and the level 2 chain from 29 to 19. In both runs, brick falls from 48 to 12, paving from 49 to 11 and landscaping from 50 to 13. Those three exterior activities now sit within a few weeks of the critical path in late fall, when the weather calendar removes three days a month.
Checking the Leveled Schedules
Each leveled run was checked in three ways before its results were used. Every relationship in the network still holds: no activity starts before its predecessors allow, and every lag is respected. The resource limit holds on every day, which the leveled histograms confirm. And no activity was split, since the script schedules each activity as one continuous block; splitting rough-in into pieces might reduce the slide further, but it would also add mobilizations the subcontractor would charge for.
Options Not Tested
Two other ways to meet the peak were considered but not run. Overtime for the existing ten electricians could cover part of the gap, but sustained overtime reduces productivity, and four weeks of it would likely lengthen rough-in rather than shorten it. Resequencing rough-in so that levels 2 and 3 run together, with level 1 later, would change crew-flow logic that the network marks as preferential, and is left for discussion with the subcontractor.
Recommendation
Adopt run three. Two extra electricians for 17 working days cost far less than losing twenty days of margin on the level 3 rough-in chain, which also carries the cover inspection that drywall on level 3 waits for. Ask the electrical subcontractor in writing to confirm twelve electricians for the window by June 15. For telehandlers, accept the brick slide but schedule a monthly review of brick and paving float through November, since their remaining margin is now small. Hinze (2012) notes that a leveled schedule is only as good as the resource commitments behind it, so the commitment, not the histogram, is the real deliverable.
Each Run's Critical Path
The critical path does not change in any run: steel through curtain wall, then interiors and closeout. In run two, however, the level 3 rough-in chain becomes near-critical, within eleven days, and is flagged on the reduced network for the update in Unit 8.
References
Hegazy, T. (1999). Optimization of resource allocation and leveling using genetic algorithms. Journal of Construction Engineering and Management, 125(3), 167-175. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:3(167)
Hinze, J. W. (2012). Construction planning and scheduling (4th ed.). Pearson.
Mubarak, S. (2015). Construction project scheduling and control (3rd ed.). Wiley.
MT381 Unit 7 instructions, in plain terms
Unit 7 asks students to load their schedule with one or more resources, compare demand with what is available and level the schedule within the limits. Instructors expect a histogram of demand from early dates, a stated limit with its source and a leveled result. The leveling method should be named and its priority rule explained. Students should report the effect on completion and, just as important, the float each activity loses. Comparing more than one staffing option, such as a strict cap and a temporary increase, is often rewarded. A recommendation should weigh the cost of extra resources against the margin preserved, and the result should be checked against both the logic and the limit.
How the MT 381 Unit 7 example is put together
The sample states each resource's assignment and limit. The early-date histogram shows where electrical overlaps occur and how often telehandler demand exceeds two. A section explains why peaks cost the subcontractor money, citing Mubarak. The serial script and its priority rule follow, with Hegazy on leveling methods. Three runs are reported with slides and remaining float, under a highlighted line that every run finishes on the same day. Telehandlers are leveled in the same pass. Spent float is itemized. Checks confirm logic and limits, untested options are noted, and the recommendation adopts the windowed run while asking for a written commitment by June 15. A last section confirms that the critical path itself never changes.
Reading the MT381 Unit 7 grading rubric
Resource leveling papers are generally assessed on the accuracy of the demand profile, the clarity of the method, the completeness of the results and the quality of the recommendation. A histogram built from the schedule's dates, with the limit marked, earns the starting marks. Naming the priority rule and showing it produces the reported slides demonstrates understanding. Rubrics reward reporting float consumed, not only the finish date. Comparing staffing options shows managerial thinking. A recommendation that prices extra resources against preserved margin, and secures a commitment, shows practical judgment. Checks that logic and limits hold protect credibility. Sources appear in APA 7, and every number in the text should match a histogram or table.
MT381 Unit 7 help from the desk
Many leveling papers show a smooth histogram and say the schedule now works, without reporting which activities moved or what float they lost. Others assume leveling always delays completion, or never does, instead of testing it. The priority rule is often unstated, so a grader cannot judge the result. Students sometimes level one resource while ignoring a second that conflicts with it. Recommendations frequently overlook that a resource limit is a commitment someone must make. Before finishing, list every activity that moved and the float it has left. If any chain is now close to critical, say so, because the next update will need to watch it, and the owner should hear it from you first.
Get an MT381 Unit 7 example written to your instructions
Attach the network and resource assignments your Unit 7 prompt uses, the crew or equipment limits it sets, and the rubric, noting any required software. The free first schedule, returned within 24-48h, levels to your limits, reports the new completion date and the float consumed, and shows exactly where the critical path moved. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.
More MT381 papers and BS in Business Administration samples
- MT381 Unit 1: Plan Vs. Schedule Discussion Post
- MT381 Unit 2: Construction Work Breakdown Structure
- MT381 Unit 3: Activity Duration Estimate Worksheet
- MT381 Unit 4: CPM Network Logic Diagram
- MT381 Unit 5: Critical Path Method Calculation
- MT381 Unit 6: Float Ownership Seminar Reflection
- MT381 Unit 8: Schedule Update Report
- MT381 Unit 9: Three-week Look-ahead
- MT381 Unit 10: Baseline Schedule Submittal
- MT362 Unit 7: AI Model Bias Review
- MT361 Unit 7: Fair Housing Listing Review
- MT359 Unit 7: Sales Promotion Proposal
- MT358 Unit 7: Influencer and Disclosure Plan
MT381 Unit 7 questions, answered
Does leveling always delay the project?
No. Leveling first shifts activities within their float, and if the peak fits there, completion holds. Only when float runs out does the finish move. The sample shows both outcomes: a short-term addition keeps the date, while a hard cap pushes completion seventeen working days later and changes the critical path.
Which activities should leveling delay first?
Most leveling routines favor activities with the least float or the earliest late start, so the ones that can wait are the ones that wait. Your software or course may use a different rule. Whatever the rule, state it, because different priorities produce different leveled schedules from the same network.
Why track float after leveling?
Because leveling spends float, and float spent now is unavailable when a delay arrives later. A schedule that ends leveling with several chains at two or three days is fragile even if the finish date held. Listing float before and after tells the reader how much protection actually remains.
Where can I find a free MT381 Unit 7 sample paper?
The complete MT381 Unit 7 resource-leveled schedule is printed here, comparing three electrician staffing runs and leveling telehandlers.
Why does the MT381 Unit 7 sample prefer the run allowing twelve electricians?
Two extra electricians for 17 working days preserve 28 of the level 3 rough-in chain's 31 days of float, while a strict cap of ten leaves only 11.