Eleven master-schedule activities become twenty-three crew tasks by zone and day in the MT381 Unit 9 three-week look-ahead, covering September 1 through 22 on the medical office building. Level 1 drywall splits into east, core and west, and a constraint log shows what each task still needs before a foreman can commit a crew to it.

What this page holds

Twenty-three zone tasks for September 1 through 22, a five-item constraint log and last week's completion rate make up MT381's Unit 9 look-ahead for the medical office building. Searches like "mt 381 unit 9 assignment example", "mt381 unit 9 sample" and "mt381 unit 9 example" land here.

What a finished MT381 Unit 9 three-week look-ahead looks like

Meant to be printed for the Tuesday foremen's meeting, the look-ahead runs five pages. Page one is a bar chart of fifteen working days, Labor Day blank, with tasks grouped by level and zone and each bar labeled with its crew size. The two anticipated weather days on the exterior calendar, September 13 and 22, are shaded on the brick and curtain wall rows only. Page two traces every task back to its master-schedule activity code, so the detail can be rolled up again at the next update. Page three is the constraint log: board stocking before the last curtain wall bay closes, the level 3 cover inspection request, hoistway turnover for the elevator installer, scaffold removal on the north face, and written confirmation of the switchgear ship date. A short record of last week's plan closes it.

How a MT381 Unit 9 example is structured

The look-ahead works from the updated schedule, not the baseline, because the trades need dates the job will actually meet. Each master activity is split only as far as a foreman needs to assign crews: level 1 hang becomes east, core and west zones, taping chases hang zone by zone four days behind, and the level 3 inspection becomes a request, the visit and a correction day. Nothing here changes logic or durations; if zone detail reveals a conflict, it goes back to the master schedule at the next update. Constraints are screened before tasks are committed. A task with an open constraint stays on the chart, shaded rather than dropped, so everyone can see what is waiting and on whom. Last week's record measures plan reliability, seventeen of twenty-two tasks completed or 77 percent, and gives the cause of each miss.

Printed for the foremen's meeting

Fifteen working days on one sheet, Labor Day blank, bars grouped by level and zone. Crew sizes sit on each bar so the drywall contractor can see eight hangers needed on the same days.

Level 1 board by zone

Hanging runs east, then core, then west, so taping can chase it zone by zone four days behind. Each zone matches a stocking location chosen when the board was delivered.

Board in before the glass

Levels 2 and 3 must be stocked on September 2 through the last open curtain wall bay, which is glazed the next day. Missing that date means carrying every sheet up the stair.

An inspection in three pieces

Level 3 cover inspection becomes a request two days ahead, the visit on September 9 and a correction day on the tenth, so drywall on that floor is never scheduled on hope.

Seventeen of twenty-two

Last week's plan finished 77 percent of its tasks. Two misses waited on inspections, one on material and two on crews pulled to another job, each cause written beside its task.

Where marks go in MT381 Unit 9

Look-aheads copied straight from the master schedule, the same bars at the same level of detail, earn little, because they add nothing a trade can act on. Credit goes to activities broken into assignable pieces by zone, floor or day, each traceable to its parent. Constraints are the second test: a look-ahead listing work without saying which materials, inspections, submittals or prior work it depends on cannot protect the plan. Tasks with open constraints scheduled as though ready undermine the document's purpose. Dates taken from the baseline rather than the latest update mislead the trades. A record of last week's completion, with reasons for each miss, tends to be credited because it shows the plan being measured. Detail that quietly rewrites master logic draws a note asking why the network was not updated instead.

Get a MT381 Unit 9 example written to your instructions

Send the current updated schedule or the activities your Unit 9 prompt names, any site constraints it mentions, and the rubric. Your free first look-ahead, ready within 24-48h, splits each activity into crew tasks by zone and day, logs every open constraint, and ties each task back to its master-schedule activity.

MT381 Unit 9 questions, answered

How is a look-ahead different from the master schedule?

The master schedule plans the whole job at activity level; a look-ahead covers the next few weeks at the level a foreman assigns work. It breaks activities into zone or daily tasks and screens each for constraints. It should detail the master logic without changing it, and its tasks should roll back up to their parent activities.

What counts as a constraint?

Anything that must be true before a crew can do the task: materials on site, a submittal approved, an inspection booked, prior work finished, equipment available, a question answered. Listing them lets the team clear constraints ahead of time instead of discovering them on the morning the crew arrives.

Why include last week's completion rate?

Because a plan is only useful if it is reliable. Counting how many committed tasks finished, and recording why the others did not, shows whether the look-ahead is realistic. Teams using the Last Planner System call this percent plan complete. Your course may name it differently; the idea is the same.