Free sample paper for GM593 Unit 5
Where the Scanner Stands: A Unit 5 Change Request Evaluation for Barcoding Chemicals During a Lab Move
[Student Name]
Purdue University Global
GM593: Project Execution With Monitoring and Control
Unit 5 Change Request Evaluation
[Instructor Name]
[Date]
The university, its relocation project, its staff and every figure are composite and illustrative; the methods cited are real.
How the Request Arrived
The chair mentioned the idea to the facilities coordinator in a hallway after a steering group meeting, as a natural improvement: the move was touching every container, so why not fix the paper inventory at the same time? The coordinator thanked the chair, said the idea would be evaluated, and logged it the same afternoon. No one started barcoding. That step matters, because informal changes from a sponsor are the ones most likely to be carried out without evaluation, simply because no one wants to tell the sponsor to wait. Logging the request turned a hallway remark into a decision the steering group would make with the costs in front of it.
The Logged Request
Change request 7. Requested by the chair of the Department of Biology, the project sponsor, in week 23. Description: apply a barcode label to every chemical container being moved and enter it into the university's new chemical inventory system, so that each lab arrives in the Life Sciences Building with a complete electronic inventory. Classification: a scope addition, not a correction, because the approved scope moves containers and their paper manifests but does not create an electronic inventory.
The Project Management Institute treats a change request as a formal proposal that must be evaluated for its effects on scope, schedule, cost and risk before a decision is made (Project Management Institute, 2021). This evaluation does that.
Scope Impact
About 9,500 chemical containers in the remaining labs have no barcode. The change adds a label and an inventory record for each, linked to the lab's room in the new building. The university's chemical inventory system already exists; the change adds data to it rather than new software.
Schedule Impact
The schedule effect depends on who does the work and where. Every container already passes through two steps: EHS sign-off of its manifest in Hollis Hall, and receipt and verification in the new building. The variance memo found that EHS sign-off is the constraint, with capacity of about 670 equivalent units a week against a plan of 1,050.
If barcoding happens in line at sign-off, EHS officers would spend about a minute and a half per container checking the label and confirming the record, about 240 hours across 9,500 containers. That time would come straight out of sign-off capacity. At the officers' current combined hours, it equals about eleven working days of sign-off, all on the flow that governs the demolition date.
If barcoding happens at the receiving dock in the new building, after containers have left Hollis Hall, it adds no time to EHS sign-off. Receiving has spare capacity, because it waits on the same queue upstream.
The same barcoding job costs eleven days of the deadline if it happens at the bottleneck and costs none if it happens downstream.
Eliyahu Goldratt's point that time lost at a constraint is lost for the whole system, while time saved elsewhere is a mirage, applies directly (Goldratt & Cox, 2004).
Cost Impact
Option A: in-line barcode station at EHS sign-off, $69,400. Two label printers and scanners, labels, and EHS overtime to recover part of the lost capacity. Even with the overtime, the forecast loses about six working days of sign-off on the deadline flow.
Option B: contract team at the receiving dock, $58,000. Two contract inventory technicians for twelve weeks, labels and scanners. EHS reviews the new records in batches after the move, outside the deadline flow. No effect on the schedule.
Option C: reject now and barcode later, about $85,500. Barcoding after the move would mean reopening every chemical cabinet in 38 labs, pulling containers, labeling and returning them, which a facilities estimate prices at about $85,500, plus disruption to research. Rejecting the change avoids cost now but costs more later.
Variations Considered and Dropped
Two narrower versions were considered. Barcoding only the hazardous containers, about 3,100 of the 9,500, would cut the in-line cost at EHS to about 80 hours, but it would still take nearly four working days from the constraint, and it would leave the inventory incomplete. Asking each lab's own staff to barcode its containers before packing would cost the project nothing directly, but the labs are still running experiments until their move dates, and principal investigators have already objected to losing staff time to the move. Neither version beat Option B on schedule or completeness.
Effect on Other Requirements
Option B touches two existing requirements. Receiving and verification must now confirm a barcode as well as a location, which adds about a minute per container at the dock, inside receiving's spare capacity. And the move's closeout report must include the inventory's completeness, which EHS will check in batches during the month after the move.
Risk Impact
Option A adds risk to the deadline. Option B adds a small risk that containers are shelved before they are labeled; the receiving procedure will require labeling before a container is placed in its cabinet. Option C adds no project risk but leaves the university without a complete chemical inventory for a year or more, which EHS considers a compliance weakness.
Recommendation
Approve Option B, a contract team at the receiving dock, at $58,000, funded from project contingency. It gives the chair what was asked for, a complete electronic inventory in the new building, without touching the constraint, and it costs less than barcoding later.
Harold Kerzner observes that sponsors often propose valuable changes informally, and that the project's job is to evaluate them with the same rigor as any other change rather than accept or dismiss them on the spot (Kerzner, 2022).
Conditions That Would Reverse the Advice
The advice would flip under either of two developments. If EHS sign-off capacity returns to its planned 1,050 units a week, the in-line station would cost far less schedule, and Option A's advantage of checking each record at sign-off might outweigh its higher price. And if the contract technicians cannot start within three weeks, the receiving dock would fill with unlabeled containers, and the change should be deferred until after the move rather than started late.
Steering Group Decision
At its meeting in week 24, the steering group approved Option B, with the condition that labeling must happen before any container is shelved. The change log records the decision, the contingency drawdown and the date the contract team starts.
References
Goldratt, E. M., & Cox, J. (2004). The goal: A process of ongoing improvement (3rd rev. ed.). North River Press.
Kerzner, H. (2022). Project management: A systems approach to planning, scheduling, and controlling (13th ed.). Wiley.
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.).
The Purdue Global GM593 Unit 5 instructions
In GM593 Unit 5 you evaluate a change request. Record the request as logged: number, requester, date, description and a classification such as scope addition or correction. Explain how it arrived, especially if a sponsor raised it informally. Analyze its effect on scope, schedule, cost and risk. For schedule, trace where the added work would fall in the workflow, because work placed on the project's constraint costs the deadline while the same work elsewhere may cost nothing. Price several options, including rejecting the change, and count the later cost of not doing it. Note narrower variations you considered, effects on other requirements and the conditions that would reverse your advice. Recommend an option and record the decision made through change control. Expect about five pages, citing change control and constraint sources in APA 7.
How the GM 593 Unit 5 example is put together
Change request 7, from the chair in week 23, is classified as a scope addition after a section shows how a hallway remark was logged before anyone acted. The PMBOK guide frames the evaluation. Scope adds labels and records for about 9,500 containers. Schedule traces two positions: at EHS sign-off, about a minute and a half per container and eleven working days of the constraint; at the receiving dock, none, which the highlighted sentence states, supported by Goldratt and Cox. Costs compare an in-line station at $69,400, a dock team at $58,000 and later barcoding at about $85,500. Variations, barcoding only 3,100 hazardous containers or asking labs to do it, are dropped. Effects on receiving and closeout follow, then risks, a recommendation citing Kerzner, conditions that would reverse it and the steering group's week 24 approval.
Where the points sit in the GM593 Unit 5 rubric
GM593 instructors grade this evaluation on whether it traces the change's real effect and prices honest options. A logged request with a clear classification earns early credit. Treating a sponsor's informal idea through the formal process shows discipline. The schedule analysis carries significant weight: locating where the work falls relative to the constraint shows understanding of why small changes can cost large delays. Options should include rejection and its later cost. Considering narrower variations and effects on other requirements shows thoroughness. A recommendation with conditions, and a recorded decision, completes the change control cycle. The Project Management Institute's PMBOK Guide, Goldratt and Cox's The Goal and Kerzner's Project Management provide the citations in APA 7.
GM593 Unit 5 help from the desk
Many GM593 Unit 5 evaluations add up the cost of a change and stop, missing its effect on the schedule. Others treat schedule impact as the hours of work added, without asking where those hours fall. A common gap is the cost of saying no: rejecting a useful change can mean paying more to do it later. Some writers approve a sponsor's request without analysis. Log the request, explain how it arrived, analyze scope, schedule, cost and risk, trace the work to its place in the flow, price options including rejection, note variations, recommend with conditions and record the decision.
Get a GM593 Unit 5 example written to your instructions
Change prompts in GM593 range from a sponsor's idea to a vendor's claim. Whichever yours describes, the evaluation needs that scenario, the Unit 5 instructions, the rubric and the baselines it will be tested against. Every option gets costed, refusal included, with the added work traced to where it lands. Expect it within 24-48h; a first custom sample carries no fee. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.
More GM593 papers and MS in Management samples
- GM593 Unit 1: Status Reports Nobody Believed Post
- GM593 Unit 2: Lab Relocation Status Report
- GM593 Unit 3: Earned Value Calculation by Account
- GM593 Unit 4: Variance Analysis Memo
- GM593 Unit 6: Seminar Reflection
- GM593 Unit 7: Corrective Action Plan
- GM593 Unit 8: Issue Log and Escalation
- GM593 Unit 9: Forecast to Completion
- GM593 Unit 10: Project Control Package
- GM592 Unit 5: Estimate Basis Worksheet
- GM591 Unit 5: Meter Replacement Business Case
- GM500 Unit 5: Matrix Structure Design Analysis
- GM586 Unit 5: Leadership Study Critique
GM593 Unit 5 questions, answered
Does a change requested by the sponsor still need an evaluation?
Yes, and arguably with more care, since nobody else in the project can easily question it. The sponsor may well approve it in the end, but the decision should rest on a documented analysis of its effect on schedule, budget and scope. The sample notes the requester's dual role openly and then evaluates the request exactly as it would any other.
Where can I find a free GM593 Unit 5 sample paper?
This page carries a full GM593 Unit 5 change request evaluation for barcoding chemicals during a university lab move, with three priced options, a constraint analysis and APA 7 references.
Why does the same work cost eleven days in one place and none in another?
At EHS sign-off, the step limiting the whole flow, every minute added per container reduces how many manifests can be signed. At the receiving dock, which has spare capacity because it waits on the same queue, the work adds no time to the deadline.
What happens if the change is rejected?
The university would need to barcode later by reopening every chemical cabinet in 38 labs, which a facilities estimate prices at about $85,500 plus disruption to research. Rejecting now saves money only in the short term.
Why log a hallway remark at all?
Informal changes from a sponsor are the ones most likely to be carried out without evaluation. Logging the idea the same afternoon turned it into a decision the steering group could make with the costs in front of it.