| Course | GM593 Project Execution With Monitoring and Control |
|---|---|
| Unit | Unit 9 |
| Paper type | Forecast to completion |
| Length | About 1,110 words, 7 pages double-spaced |
| Format | APA 7 student paper |
| School | Purdue University Global |
| Program | MS in Management |
| Updated | October 2026 |
Free sample paper for GM593 Unit 9
Seventy Percent of Items, Fifty-Two Percent of the Work: A Unit 9 Forecast to Completion for a Lab Relocation
[Student Name]
Purdue University Global
GM593: Project Execution With Monitoring and Control
Unit 9 Forecast to Completion
[Instructor Name]
[Date]
The university, its relocation project and every figure are composite and illustrative; the methods cited are real.
Summary
The Hollis Hall relocation is forecast to finish in about 13.5 months against a 12-month plan, within a range of 13.0 to 14.0 months. The final cost is forecast at about $2,627,600 against a budget at completion of $2,360,000, within a range of $2,593,400 to $2,675,300. The recommended points assume the corrective actions hold sign-off capacity near its current level and that Hollis Hall stays open one month past its planned closing.
Forecasting the Finish: Three Methods
Counting items. At the end of month eight, 22,150 of 31,400 items have been scanned, leaving 9,250. Over the last four weeks, the project has scanned about 820 items a week. At that rate the remaining items would take about 11.3 weeks, finishing about six weeks before the planned end. This method treats every item as the same, which is the problem.
Counting equivalent units. Weighted by effort, the whole inventory comes to about 43,440 equivalent units, of which about 22,590 are done, or 52 percent. The remaining items carry about 20,850 units, an average of 2.25 per item, compared with about 1.0 for the items already moved. The project has demonstrated about 1,030 units a week since the corrective actions took effect. At that rate the remaining work would take about 20.2 weeks, finishing packing about three weeks after the planned end, with transport and receiving still to follow.
The labs moved first held mostly instruments; the labs still waiting hold most of the freezers and hazardous chemicals, so counting items makes the hardest work look like the smallest part.
Earned schedule. Walt Lipke's earned schedule method converts earned value into time, by finding the date on the baseline when the work now earned was planned to be complete (Lipke, 2003). At the end of month eight, the project's earned value matches the baseline for about month 7.0, giving a time-based schedule performance index, SPI(t), of about 0.874. Dividing the planned 12 months by 0.874 forecasts about 13.7 months. Unlike the cost-based SPI, which drifts toward 1.0 as a late project nears its end, SPI(t) keeps its meaning to completion.
The cost-based SPI tells a different and misleading story here. At 0.912 it suggests the project is less than 10 percent behind. But that index is a ratio of dollars, and at the end of any project earned value must equal planned value, so the cost-based SPI rises toward 1.0 even for a project that finishes months late. Lipke designed earned schedule to avoid this drift, which matters most in the last third of a project, where this relocation now sits.
The recommended finish of 13.5 months sits between the equivalent unit forecast, which covers packing only, and the earned schedule forecast for the whole project.
Forecasting the Final Cost: Four Estimates
At the end of month eight, earned value is $1,587,500, actual cost $1,744,500, the cost performance index 0.910 and the cost-based schedule performance index 0.912.
If past overruns were one-off. EAC equals actual cost plus the remaining budgeted work: $1,744,500 plus $772,500, or $2,517,000. This assumes future work will run exactly to budget, which the record does not support.
At the current CPI. EAC equals the budget at completion divided by the CPI: $2,360,000 divided by 0.910, or about $2,593,400.
With both indexes acting. EAC equals actual cost plus the remaining work divided by the product of CPI and SPI: $1,744,500 plus $772,500 divided by 0.830, or about $2,675,300. This assumes schedule pressure will raise costs as well, which fits a project now paying for extra signing help.
Bottom-up. Each control account's remaining work was re-estimated by its owner, and one month of holdover cost for Hollis Hall was added: utilities, security and the demolition contractor's standby charge, about $57,000. The total is about $2,627,600.
Frank Anbari notes that the index-based formulas are useful checks but rest on assumptions about future performance, and that a bottom-up estimate is worth the effort when conditions have changed (Anbari, 2003). The corrective actions changed the project's conditions in month six, so the bottom-up figure is the recommended point.
Checking the Forecasts Against Each Other
The three date methods and four cost estimates do not need to agree, but their disagreements should be explainable. The item count disagrees with the other two date methods because it ignores effort, and it is set aside for that reason. The equivalent unit forecast and earned schedule differ by about a month, because the first covers packing alone and the second the whole project, including transport and receiving. On cost, the one-off estimate is the outlier because it assumes a sudden return to budget that eight months of data contradict. The bottom-up figure falls between the CPI estimate and the combined-index estimate, which is what a reader would expect from a project that has fixed its main cause but is still paying for the fix.
Assumptions Behind the Recommended Points
The recommended finish assumes weekly sign-off stays at or above 1,030 equivalent units, that the contract safety specialist stays for the full ten weeks and that no lab requests a further delay. The recommended cost assumes one month of holdover, no second month, and recovery of none of the fan rework cost, which is still in dispute with the design firm. Each assumption has an owner who will report on it weekly.
What Would Move the Forecasts
Three conditions would move the forecasts most. If EHS sign-off capacity falls again, for example if the contract safety specialist leaves early, the finish would slip by about a week for every two weeks of reduced capacity. If the remaining ultra-low freezers fail qualification at the rate the first two did, biological labs would wait, and the finish could reach the top of the range. If the demolition contractor will not accept a one-month delay, the university would face either overtime to finish on time or a larger standby charge, and the cost forecast would rise.
Quentin Fleming and Joel Koppelman recommend reporting a forecast as a range with a stated basis, rather than a single figure, so that decision makers can see how much the estimate depends on its assumptions (Fleming & Koppelman, 2010). The steering group should decide now whether to negotiate the month of holdover with the demolition contractor, while the forecast still allows a choice.
References
Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23. https://doi.org/10.1177/875697280303400403
Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.
Lipke, W. (2003). Schedule is different. The Measurable News, 31-34.
The Purdue Global GM593 Unit 9 instructions
GM593 Unit 9 asks you to forecast a project's finish date and final cost. Open with a summary giving each forecast as a range with a recommended point. Forecast the date with more than one method, such as counting units, counting effort-weighted units and earned schedule, and explain why they differ. Show why the cost-based SPI can mislead late in a project. Forecast cost with several estimates at completion, each with its formula and its assumption about the future, and add a bottom-up estimate where conditions have changed. Check the forecasts against each other and explain the disagreements. State the assumptions behind your recommended points, each with an owner. Close with what would move each forecast and the decision the forecast makes possible now. Expect about five pages with a summary table, citing earned value and earned schedule sources in APA 7.
How the GM 593 Unit 9 example is put together
The summary gives 13.5 months within 13.0 to 14.0, and $2,627,600 within $2,593,400 to $2,675,300. Item counting gives an early finish because it ignores effort. Equivalent units show about 22,590 of 43,440 done and 2.25 units per remaining item against about 1.0 so far, which the highlighted sentence explains. Lipke's earned schedule gives an SPI(t) of 0.874 and 13.7 months, and a paragraph shows why the cost-based SPI of 0.912 drifts toward 1.0. Cost estimates follow: $2,517,000 if overruns were one-off, $2,593,400 at a CPI of 0.910, $2,675,300 with both indexes and $2,627,600 bottom-up with $57,000 of holdover, preferred per Anbari. A section reconciles the methods and another lists assumptions with owners. Risks to the forecast and Fleming and Koppelman on ranges lead to a decision about negotiating holdover with the demolition contractor.
GM593 Unit 9 rubric: what earns full points
GM593 instructors grade this forecast on method, honesty about uncertainty and usefulness to a decision. A summary with ranges and recommended points earns early credit. Using several date methods, and explaining why counting items and counting effort disagree, shows understanding of how progress is measured. Explaining earned schedule and the drift in the cost-based SPI carries weight late in a project. Each cost estimate should state its formula and assumption, and a bottom-up estimate should be justified when conditions changed. Reconciling the methods shows the forecasts were checked. Assumptions with owners and a list of what would move the forecast make it manageable. Ending on a decision the forecast allows shows practical value. Anbari in Project Management Journal, Fleming and Koppelman and Lipke's earned schedule article supply the citations in APA 7.
GM593 Unit 9 help: mistakes that cost points
Many GM593 Unit 9 forecasts use one formula and report a single number, hiding how much the result depends on its assumption. Others count units of very different difficulty as equal, which makes a late project look early when the hardest work is left. A common gap is late-project drift: the cost-based SPI rises toward 1.0 near the end, so earned schedule is worth adding. Some writers forecast without saying what decision the forecast supports. Summarize ranges and points, use several date methods, weight progress by effort, compare cost formulas and a bottom-up figure, reconcile them, state assumptions and name the decision.
Get a GM593 Unit 9 example written to your instructions
Forecast prompts supply different data: indexes only, a full progress history, or a schedule with remaining work. Paste in whichever your Unit 9 case gives, along with the rubric and any EAC methods your reading names. Date and cost are both projected, each method labeled with its assumption, and the forecast returns in 24-48h. A first custom sample is free. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.
More GM593 papers and MS in Management samples
- GM593 Unit 1: Status Reports Nobody Believed Post
- GM593 Unit 2: Lab Relocation Status Report
- GM593 Unit 3: Earned Value Calculation by Account
- GM593 Unit 4: Variance Analysis Memo
- GM593 Unit 5: Change Request Evaluation
- GM593 Unit 6: Status Reporting Seminar Reflection
- GM593 Unit 7: Corrective Action Plan
- GM593 Unit 8: Issue Log and Escalation Matrix
- GM593 Unit 10: Project Control Package
- GM592 Unit 9: Quality and Reporting Plan
- GM591 Unit 9: Portfolio Capacity Review
- GM500 Unit 9: Six-Box Diagnosis of Crew Turnover
- GM586 Unit 9: Behavior Development Plan
GM593 Unit 9 questions, answered
What is earned schedule and when is it worth using?
Earned schedule expresses the schedule gap as months instead of money: it finds the date by which the plan expected the value actually earned and compares that date with today. It avoids the familiar distortion in which the dollar-based SPI drifts back toward one near the end, so it is worth including wherever the finish date matters as much as cost.
Should the forecast give a range or a single figure?
Both, where possible. A range shows the uncertainty honestly; a recommended point inside it gives the sponsor something to plan against. The sample states each range, marks its preferred figure, and names the events that would push the result toward either edge, which is what turns a forecast from a number into something a steering group can use.
Where can I find a free GM593 Unit 9 sample paper?
This page carries a full GM593 Unit 9 forecast to completion for a university lab relocation, with three date methods, four estimates at completion, ranges and APA 7 references.
Why do items and equivalent units give opposite forecasts?
The labs moved first held mostly instruments, averaging about 1.0 equivalent unit per item, while the remaining items average 2.25. Counting items treats the hardest remaining work as if it were as easy as the work already done.
Why is the bottom-up estimate recommended?
The corrective actions changed the project's conditions in month six, so formulas based on past indexes may not describe the future. The bottom-up estimate re-prices remaining work by account and adds about $57,000 for a month of holdover at Hollis Hall.