Three Weeks Promised, Eleven Delivered: Unit 1 Discussion on an Estimate Built From a Picture
MT246 · Unit 1 Discussion Board Post
Posted by [Student Name]
Harlan Street Barbecue, its staff, the city offices and every date are composite and illustrative; the sources cited are real.
Initial Post
In January the owner of the barbecue restaurant where I manage catering asked how long it would take to turn our back storage room into a prep kitchen for catering orders. Our catering season opens in April. I pictured the finished room, a steel prep table, a sink, a reach-in cooler and two warmers, and said three weeks that same afternoon. The room passed its final inspection in late March, eleven weeks after I answered.
My three weeks left out almost everything that was not carpentry. The city's pretreatment office required a grease interceptor for the new sink, which meant a plumber, a permit and a concrete cut in the floor. The health department's plan review took eighteen working days in its queue before anyone looked at our drawings. The warmers needed a second electrical circuit, and the electrician could not start until the plan was approved. And we failed the first inspection because the handwash sink was more than twenty feet from the prep table, which meant moving it and waiting for a second inspection.
In the studies of Buehler et al. (1994), students forecasting their own assignments pictured how the work would go well and set aside their history of finishing late, though they could recall it when asked. That was me: I had watched our dining room remodel run over two years earlier and still pictured a clean three weeks. Kahneman and Lovallo (1993) call this the inside view, building a forecast from the particulars of one plan, and contrast it with the outside view, which asks how long projects like this one usually take. If I had asked any restaurant owner how long a health department plan review takes, the queue alone would have told me three weeks was impossible.
I estimated the room I could see and skipped the offices I could not.
This term I am planning a food truck launch for the same restaurant. This time I will list every approval before estimating any work, and I will ask two other owners how long their trucks took from purchase to first sale. What outside view have you used, or wished you had used, on an estimate of your own?
Reply to Dana
Dana, your bathroom remodel estimate sounds like mine: the tile work was right, but the plumbing inspection and the backordered vanity were invisible when you gave the number. Did your contractor give a range, or a single date like I did?
Reply to Victor
Victor, I like that your warehouse estimates start from last year's actual times. I wonder whether that works for a one-time job like a racking change, where there may be no past record. Where would you find the outside view then?
References
Buehler, R., Griffin, D., & Ross, M. (1994). Exploring the "planning fallacy": Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366-381. https://doi.org/10.1037/0022-3514.67.3.366
Kahneman, D., & Lovallo, D. (1993). Timid choices and bold forecasts: A cognitive perspective on risk taking. Management Science, 39(1), 17-31. https://doi.org/10.1287/mnsc.39.1.17
Reading the MT 246 Unit 1 instructions
Students open MT 246 by describing an estimate, their own or one they watched, that turned out badly wrong, and explaining why. The prompt asks for specifics: what the estimate was, what actually happened and which pieces of work the estimate left out. Then it wants a concept from the readings applied to the reasoning behind the number, such as the planning fallacy or the difference between the inside and outside views. A good post ends with how the writer will estimate the project they plan this term. Your own estimate gives the most honest material, since you can describe what you were thinking. Cite the readings in APA 7, keep the first post to roughly 300 to 400 words and answer two classmates during the week.
Inside the MT246 Unit 1 example
The post's opening paragraph sets the January question, the April catering season and the three-week answer given the same afternoon. Paragraph two lists the missing work: the interceptor the pretreatment office required, the eighteen-day plan review queue, the warmers' circuit and the failed inspection. Buehler and colleagues' finding that people forecast their own tasks from a success story is applied to the writer's memory of a remodel that also ran late, and Kahneman and Lovallo's outside view shows how one question to another owner would have exposed the queue. The highlighted line says the estimate covered the room and skipped the offices. A closing paragraph commits to listing approvals first and asking two owners for the food truck. Replies ask Dana whether her contractor gave a range and Victor where the outside view comes from for a one-time job.
Reading the MT246 Unit 1 grading rubric
For a first estimating post, most of the credit depends on showing exactly what the estimate left out, with dates or counts, rather than saying it was optimistic. Applying a reading to the writer's own reasoning, not just to the outcome, shows understanding of why estimates fail. Graders look for the outside view or a similar idea used correctly, and for a concrete plan to estimate differently. Two replies that ask a real question or test a classmate's explanation earn the participation share. APA citations for both readings and posting early enough for discussion account for the rest. A post that admits the writer's own mistake plainly usually reads as stronger than one that blames others, and staying near the word limit keeps it readable for classmates.
MT246 Unit 1 help: mistakes that cost points
The most common slip is describing a project that ran late without identifying the estimate behind it, which leaves nothing to analyze. Another is blaming the delay on outside parties, such as an inspector, without asking why the estimate did not allow for them. Some posts define the planning fallacy and never connect it to their own thinking. Others end with a general resolution, such as add padding, instead of a method. Replies that only praise a classmate's honesty earn little. Describe an estimate you gave and what happened, and a writer will draft a post that lists what it missed and applies the readings to your reasoning.
Get an MT246 Unit 1 example written to your instructions
Think of an estimate that ran long, one you gave or one you watched someone give, and jot down what it turned out to leave out. Paste that list beside the Unit 1 board question, its reply requirements and the rubric. A first post costs nothing, returns within 24-48h, and names every person only by role. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.
More MT246 papers and BS in Business Administration samples
- MT246 Unit 2: Work Breakdown Structure
- MT246 Unit 3: Estimating Exercise
- MT246 Unit 4: Network and Critical Path
- MT246 Unit 5: Project Schedule
- MT246 Unit 6: Seminar Reflection
- MT246 Unit 7: Cost Baseline
- MT246 Unit 8: Resource Assignment Plan
- MT246 Unit 9: Status Report
- MT246 Unit 10: Change Request Package
- MT245 Unit 1: Discussion Board Post
- MT243 Unit 1: Discussion Board Post
- MT242 Unit 1: Discussion Board Post
- MT241 Unit 1: Discussion Board Post
MT246 Unit 1 questions, answered
Does the estimate have to be one I made myself?
Not always, though the post is usually stronger when it is. An estimate someone else gave can work if the post can say what it was based on and what it missed. The example uses the writer's own number because the planning fallacy concerns how people forecast their own work, and that reading lands harder when a writer applies it to himself.
What is the difference between the inside view and the outside view?
The inside view builds a forecast from the details of this particular job as the planner imagines them. The outside view starts from how long similar jobs actually took elsewhere, then adjusts. Kahneman and Lovallo argued that planners lean on the first and neglect the second. The example shows what one outside-view question, put to two nearby owners, would have produced.
Should the post end with a rule for better estimates?
A modest one helps, provided someone could actually follow it. A vow of extra care reads as filler. The example commits to two concrete habits for its next project: an estimate built from jobs each assignable to one person, and a comparison with how long other food trucks took to launch. It stops short of claiming either habit guarantees accuracy.
Where can I find a free MT246 Unit 1 sample paper?
Read the complete MT246 Unit 1 discussion board post here. It takes apart a three-week estimate for a restaurant prep kitchen that took eleven, using the planning fallacy and the inside and outside views, with two replies.
What did the estimate leave out in the MT246 Unit 1 sample?
A grease interceptor the city required, eighteen working days in the health department's review queue, a second electrical circuit for the warmers and a failed first inspection over the handwash sink's position.