MT246 Unit 9 Status Report Example

Reviewed by Chester Goodwin, MBA Project Planning and Project Execution Purdue University Global Free custom sample in 24 to 48h

The MT246 Unit 9 status report on a composite barbecue restaurant's food truck, dated Friday, May 1, opens with one line for the owner: the money is on plan and the dates are not. Plan approval came three working days late after a sink drawing revision, and a backordered exhaust hood adds four more, so the upfit finishes May 28 instead of May 18 and the ready date would land on July 3, the day city offices close for the Fourth. Purdue Global MT 246 asks for a sponsor status report in Unit 9, and the sample gives a milestone table with variances, a buffer balance, progress by deliverable and earned value of $91,841 against $92,576 spent. A recovery of two upfitter Saturdays and a faster wrap buys back three days. Two dated decisions close the memo, written for the BS in Business Administration.

CourseMT246 Project Planning and Project Execution
UnitUnit 9
Paper typeStatus report
LengthAbout 830 words, 6 pages double-spaced
FormatAPA 7 student paper
SchoolPurdue University Global
ProgramBS in Business Administration
UpdatedOctober 2026

Free sample paper for MT246 Unit 9

1

Money on Plan, Dates Not: A Unit 9 Status Report on a Food Truck Seven Days Behind on May 1

[Student Name]

Purdue University Global

MT246: Project Planning and Project Execution

Unit 9 Status Report

[Instructor Name]

[Date]

Harlan Street Barbecue, its vendors, dates and every figure are composite and illustrative; the sources cited are real.

What this part is doingPutting the verdict in the first line lets the owner know in five seconds whether to keep reading.
2

To: Owner, Harlan Street Barbecue From: Catering Manager Date: Friday, May 1 Re: Food truck project status, week 9

Summary

The money is on plan and the dates are not. Plan approval came three working days late and the upfitter's exhaust hood is backordered by four more, so the upfit now finishes on May 28 instead of May 18. Without action, the truck would be ready on Friday, July 3, the day city offices close for the holiday, which leaves no time to fix any inspection problem before Riverfest. I recommend a recovery that buys back three days and ask for your decision by Wednesday.

Milestones

Each milestone shows the planned date, the actual or forecast date and the variance in working days.

Plan approved: planned March 4; actual March 4; 0

Health plan review approved: planned April 6; actual April 9; 3 late

Upfit begins: planned April 7; actual April 10; 3 late

Upfit accepted: planned May 18; forecast May 28; 7 late

Fire marshal sign-off: planned May 26; forecast June 4; 7 late

Health permit issued: planned June 1; forecast June 10; 7 late

Ready for launch: planned June 24; forecast July 3; 7 late

Riverfest: July 4; fixed

Buffer: six days in the baseline after the soft launch moved past Father's Day; minus one at today's forecast; back to two if the recovery below is approved, since it buys back three days.

What this part is doingReporting the buffer as a running balance shows the owner how much protection is left, not only how late the work is.
3

Why the Dates Moved

Two causes, neither the team's doing. The PMBOK Guide asks that variances be explained by cause, not only measured (Project Management Institute, 2021), so the owner can tell whether the problem will recur. The health department's reviewer asked for a revised drawing of the handwash sink location, which took three working days to answer, so plan approval came on April 9 instead of April 6. The upfitter could not start until it had the approved plan, so its start moved from April 7 to April 10. Then on April 27 the upfitter's supplier reported that the exhaust hood specified in the plan is backordered and will arrive May 14 instead of May 8. The hood must be installed before the fire suppression system and the generator wiring, so the upfit's finish moves four more days, to May 28.

Progress by Deliverable

Ten of the eleven activities due by today are finished: plan approval, the upfitter's layout, plan review, the van purchase and inspection, the commissary letter, the draft menu, the insurance binder, menu testing, the hiring posting and the wrap design proof. The eleventh, the final wrap file, waits for menu photos and is one day late, with about four weeks of float. The upfit is sixteen working days in against nineteen planned, and the upfitter reports cabinetry and the water system complete. The catering booking calendar for the truck's first six weeks after Riverfest has four weeks filled.

Cost

Work completed so far is valued at $91,841 at budgeted rates. Actual spending is $92,576. The baseline planned $92,449 by the end of April. Spending is about $735 above the value of the work done, less than one percent, and the work done is about $608 short of plan, which matches the three-day late start. Fleming and Koppelman (2010) describe this comparison of earned value with actual cost and planned value as the way to separate cost problems from schedule problems, and here the cost side is sound.

The project is spending at the rate it should; it is simply spending it three days later.

Recommended Recovery

The upfitter has offered to work two Saturdays, May 16 and 23, for $1,900 in overtime, which recovers two days. The wrap shop has agreed to install in four days instead of five if the truck arrives clean, which recovers one more. Together they bring the ready date from July 3 to Tuesday, June 30, with two buffer days before city offices close. The overtime would come from contingency, which has $9,619 unspent.

Decisions Needed

Decision 1, by Wednesday, May 6: approve the upfitter's two Saturdays at $1,900 from contingency. Without approval by then, the upfitter will release the Saturday crew to another job.

Decision 2, by Monday, May 11: if the hood has not shipped by May 11, approve a fallback, a comparable hood from a second supplier at $640 more, available in two days. The fallback needs a one-page amendment to the health plan, which the reviewer has said she can turn around in two working days. Larson and Gray (2021) recommend that status reports end with decisions the sponsor can make by a date, so that a report produces action rather than only information.

What this part is doingGiving each decision a deadline and the cost of missing it turns the report into something the owner can act on this week.
4

References

Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.

Larson, E. W., & Gray, C. F. (2021). Project management: The managerial process (8th ed.). McGraw-Hill.

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.

Reading the MT 246 Unit 9 instructions

Unit 9 asks students to write a status report to the project's sponsor at a point when something has gone wrong. The prompt usually expects a short summary first, a milestone table with planned, actual or forecast dates and variances, progress stated by deliverable, a cost section and the decisions the sponsor must make. Many sections ask for earned value or another comparison of work done, money spent and work planned. Explain each variance by its cause. Recommend a recovery and say what it costs, and give each decision a deadline and the consequence of missing it. Two pages plus an appendix is common, written for a reader with five minutes, with sources cited in APA 7.

How the MT 246 Unit 9 example is put together

The memo header and three-line summary state the verdict and the request, under a margin note on leading with it. A milestone table gives eight dates with variances, followed by the buffer as a running balance, marked by a second note. A section explains the causes, the reviewer's sink drawing and the hood backorder, with the PMBOK Guide on explaining variances. Progress lists ten of eleven due activities finished and the upfit at sixteen days of nineteen. The cost section compares earned value, actual cost and plan, citing Fleming and Koppelman, and the highlighted line says the project spends at the right rate three days later. A recovery and two decisions with deadlines close it, with Larson and Gray.

Where the points sit in the MT246 Unit 9 rubric

Status reports earn marks for a clear verdict, accurate variances, honest causes and decisions the sponsor can act on. Putting the bottom line first matters because sponsors may read nothing else. Graders reward milestone tables with forecasts, not only plans, and progress stated by deliverables rather than percentages of effort. Earned value or a similar comparison earns credit when it separates cost from schedule problems. A recovery option should be priced and its effect on the buffer shown. Decisions with deadlines and the cost of delay show the report is a management tool. Brevity, consistency with the baseline figures and correct citations take the remaining points.

Common MT246 Unit 9 mistakes, and how to avoid them

Reports most often fail by listing what everyone did this week and never saying whether the project is on track. Another is variances with no cause, which leaves the sponsor unable to judge whether they will recur. Some reports present earned value figures without explaining what they mean. Others ask the sponsor to decide without a deadline, so the decision drifts past the point where it helps. Avoid blaming vendors; state causes plainly, with dates, so the sponsor can judge whether the same thing could happen again. Send your baseline and current dates, and a writer can draft the summary, milestone table and decisions for your sponsor.

Get an MT246 Unit 9 example written to your instructions

Measured against what? A status report needs the earlier schedule and budget as its baseline, plus whatever progress figures the case gives for the reporting date and the Unit 9 prompt and rubric. Within 24-48h the first report comes back free, leading with what changed and what the sponsor must decide. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.

More MT246 papers and BS in Business Administration samples

MT246 Unit 9 questions, answered

Should the report include earned value?

Only if your course has taught it by this unit. The example uses a simple version, crediting finished work at its budget and half for work under way, because the owner wanted a check on spending. It adds no indices. Where earned value is required, the same figures extend easily; where it is not, the milestone table and buffer line carry the report on their own.

Why lead with a problem the team did not cause?

Because the sponsor needs the effect whatever the cause. The report does name the causes, a review queue and a backorder, but only after stating what they did to the launch date. Leading with where blame belongs, or with accomplishments, delays the part the owner has to act on. Early, plain reporting of a slip is what most rubrics reward.

What goes in a fallback decision?

What happens if the recovery fails, what it costs to prepare, and when the sponsor must choose. The example proposes serving Riverfest from the restaurant's catering tent under a temporary event permit if the truck lacks its health permit by June 26. Deciding by May 15 leaves time to apply. Framing it early keeps the choice a plan rather than a scramble.

Where can I find a free MT246 Unit 9 sample paper?

You can read the complete MT246 Unit 9 status report here. It reports a food truck project seven working days behind on May 1, with a milestone table, buffer balance, earned value and two dated decisions.

How does the MT246 Unit 9 sample show the money is on plan?

Work completed is valued at $91,841 against $92,576 spent and $92,449 planned, so spending runs less than one percent above the value of work done, and the shortfall against plan matches the three-day late start.