HI300 Unit 5 Implementation Checklist Example

Reviewed by Chester Goodwin, MBA Information Systems for Health Care Purdue University Global Free custom sample in 24 to 48h

This HI300 Unit 5 implementation checklist takes a composite labor and delivery unit from paper flowsheets to a live perinatal system in four phases. Purdue Global HI 300 expects BS in Health Information Management students to sequence conversion, testing, go-live and early support, and every task here carries an owner and a done test. Old flowsheets stay on paper while prenatal summaries flow in electronically. Testing runs in three layers, ending with nurses charting a whole composite labor. Two decisions are signed before go-live at 06:00 on a Tuesday: patients already in labor stay on paper until delivery, and a thirty-minute loss of bedside tracings triggers a return to paper. The first twenty-one days move from round-the-clock support to a review of workarounds.

CourseHI300 Information Systems for Health Care
UnitUnit 5
Paper typeImplementation checklist
LengthAbout 880 words, 6 pages double-spaced
FormatAPA 7 student paper
SchoolPurdue University Global
ProgramBS in Health Information Management
UpdatedOctober 2026

Free sample paper for HI300 Unit 5

1

Conversion, Testing and the First Twenty-One Days: A Unit 5 Implementation Checklist Taking a Labor and Delivery Unit From Paper Flowsheets to a Live Perinatal System

[Student Name]

Purdue University Global

HI300: Information Systems for Health Care

Unit 5 Implementation Checklist

[Instructor Name]

[Date]

The hospital, dates and staffing are composite; the practices described and the sources cited are real.

What this part is doingGiving every task an owner and a done test turns the checklist into something a project manager can actually close, not a list of intentions.
2

Phase 1: Build and Conversion, Weeks 1 to 8

The build phase sets up the system to match the unit rather than the vendor's model unit. Owner: the information services analyst, with the unit's nurse educator. Done test: every location on the unit, including the two operating rooms and four recovery bays, exists in both the perinatal system and the main record, and a composite patient can be moved through all of them. Conversion is smaller than in most projects, because the unit charts on paper. The team decided not to scan old flowsheets into the new system. Patients delivered before go-live keep their paper record in the HIM department, and the main record notes where it is. The one exception is prenatal records from the hospital's own clinics, which are already electronic and must flow into the new system before go-live. Owner: the HIM analyst. Done test: prenatal summaries for ten composite patients display correctly on the labor unit.

Phase 2: Testing, Weeks 9 to 12

Testing runs in three layers. Unit testing checks each form and alert as built. Integration testing sends composite patients through every interface flow, including a transfer to the operating room, a newborn birth and a discharge, and checks each against the expected result. Scenario testing has labor nurses chart a full composite labor, from admission to delivery, at the bedside, while a second nurse times the work and records each problem. Owner: the project lead. Done test: no open defect rated severe, and every moderate defect has an owner and a date. Training happens alongside testing. Every nurse, midwife and obstetrician completes four hours of hands-on training within the three weeks before go-live, not earlier, because skills fade quickly when they are not used. Each shift also gets two super users, nurses who receive a further day of hands-on practice and become the first person their colleagues ask. The scenario test is the only one in which a nurse charts a whole labor. It is also the test most often cut when a schedule slips, and that cut is the one this checklist forbids. Training content follows the requirements rather than the vendor's standard course. The scenario that nurses practice is the night shift the analyst observed: three laboring patients, one with a category II tracing, one moved to the operating room and one delivering at the bedside. Physicians train on the same scenario from their side, entering orders and signing the delivery note. Training that rehearses the unit's own hardest night is more useful than a tour of every screen.

What this part is doingTying training to the observed night shift links this checklist back to the requirements, which graders reward as evidence of a coherent project.
3

Phase 3: Go-Live, Day 0

Go-live is set for 06:00 on a Tuesday, chosen because the scheduled induction list is shortest that morning and the full project team is on site. Two decisions are written down and signed before the day. First, patients already in labor at 06:00 stay on paper until delivery. Moving a laboring patient's chart mid-labor risks losing the sequence of interpretations at the moment it matters most. Every patient admitted after 06:00 is charted electronically. Second, the rollback rule. If the system cannot display tracings at the bedside for more than thirty minutes during the first twenty-four hours, the unit returns to paper and the project team decides within four hours whether to try again. Owner: the chief nursing officer. Done test: the rule is signed and posted at the nurses' station.

What this part is doingWriting the rollback rule before go-live means nobody has to invent a decision under pressure at three in the morning.
4

Phase 4: The First Twenty-One Days

Days 1 to 7: super users and vendor staff are on the unit around the clock. A command center log records every problem with the time, the room and the fix. The project lead reviews the log twice a day. Days 8 to 14: support moves to the day and evening shifts, with a phone line at night. The educator observes three charted labors each day and records the time to enter an interpretation, compared with the target of three actions set in the requirements. Days 15 to 21: the team reviews the log for patterns, such as the same alert ignored repeatedly or a form bypassed with a free-text note. Workarounds discovered here are the early signs of a design problem rather than a training problem, a distinction the literature on unintended consequences of clinical systems makes clear (Ash et al., 2004).

What Makes the Checklist Work

The checklist reflects three lessons from the literature on large implementations: bring in the staff who will chart in it, test with real work rather than features, and plan for the first weeks of live use as a phase in its own right (Cresswell et al., 2013). It also respects a point from studies of system downtime, that a plan for when the technology fails belongs in the implementation from the start (Larsen et al., 2018). The unit's downtime procedure is written and practiced in Phase 2, not after the first outage.

5

References

Ash, J. S., Berg, M., & Coiera, E. (2004). Some unintended consequences of information technology in health care: The nature of patient care information system-related errors. Journal of the American Medical Informatics Association, 11(2), 104-112. https://doi.org/10.1197/jamia.M1471

Cresswell, K. M., Bates, D. W., & Sheikh, A. (2013). Ten key considerations for the successful implementation and adoption of large-scale health information technology. Journal of the American Medical Informatics Association, 20(e1), e9-e13. https://doi.org/10.1136/amiajnl-2013-001684

Larsen, E., Fong, A., Wernz, C., & Ratwani, R. M. (2018). Implications of electronic health record downtime: An analysis of patient safety event reports. Journal of the American Medical Informatics Association, 25(2), 187-191. https://doi.org/10.1093/jamia/ocx057

The Purdue Global HI300 Unit 5 instructions

Unit 5 typically asks for an implementation plan or checklist for a system already selected. You are expected to sequence the work in phases, usually build or conversion, testing, training, go-live and post-live support, and to name who is responsible for each task. Many prompts ask how existing records will be handled, whether converted, scanned or left in place. Expect questions about testing levels and about what happens if go-live fails. Some instructors want a timeline in weeks, others a table of tasks and owners. Training timing is a common grading point, since training too early wastes it. A short justification drawing on implementation research is usually required. Keep the plan specific to one setting; a generic checklist that would fit any system tends to score lower.

How the HI 300 Unit 5 example is put together

Each of the four phases has its own section with tasks, owners and done tests. The build phase covers locations in both systems and the decision not to scan old paper. The testing phase describes unit, integration and scenario testing, plus training timed in the three weeks before go-live and two super users a shift. Training content is tied to the observed night shift. A highlighted line insists the scenario test is never cut. The go-live section records the start time, the rule for patients already in labor and the signed rollback rule. The final phase moves support from round the clock to a phone line and reviews the log for workarounds. A closing section links the plan to research on adoption, unintended consequences and downtime.

Reading the HI300 Unit 5 grading rubric

Implementation plans in this course are usually graded on sequence, ownership and risk planning. Sequence points reward phases that run in a sensible order, with testing before training ends and training close to go-live. Ownership points require named roles for tasks, not just a list of activities. Risk planning carries a large share: graders look for a cutover decision for patients mid-process, a rollback rule and a plan for the first weeks. Handling of existing records is often its own item. Instructors also reward measurable done tests that let a manager close a task. Research support, clear formatting and APA citations make up the rest. Plans that end at go-live, with no early support phase, commonly lose credit even when everything before it is strong.

HI300 Unit 5 help: mistakes that cost points

The most frequent gap is ending the plan on go-live day, as if the work stopped there. Another is scheduling training months ahead, so staff forget it before they need it. Many plans skip the patients already in process at cutover, which on a labor unit means women mid-labor. Rollback rules are often missing or vague. Testing sections that list only vendor testing miss the scenario test with real staff. Some students assign every task to the project team rather than to named roles. We can write the implementation checklist for the system and setting in your assignment, with owners, done tests and a cutover plan. Send the scenario, the system chosen, the timeline you were given and any template, and mention whether conversion of old records is part of the task.

Get an HI300 Unit 5 example written to your instructions

Implementation prompts differ in scope, so say which departments your Unit 5 case takes live and attach the instructions and rubric. The checklist is then built for that go-live, phases, owners and gates included, and returned in 24-48h, with no fee for your first sample. Conversion choices follow any data your case describes. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.

More HI300 papers and BS in Health Information Management samples

HI300 Unit 5 questions, answered

Where can I find a free HI300 Unit 5 sample paper?

This page holds the full Unit 5 implementation checklist, four phases from build to the first twenty-one days, each task with an owner and a done test.

What is a rollback rule?

A decision written before go-live stating when the unit returns to its old process and who decides. The sample sets thirty minutes without bedside tracings as the trigger.

When should staff be trained on a new system?

Close to go-live, usually within the last few weeks, so skills are fresh. The sample trains every clinician in the three weeks before the start date.

What happens to patients already in labor at go-live?

In the sample they stay on paper until delivery, because moving a chart mid-labor risks losing the order of interpretations.

What is a super user?

A staff member given extra training who supports colleagues on the unit during go-live. The sample assigns two to each shift.