GM594 Unit 9 Ethics Case Analysis Example

Reviewed by Chester Goodwin, MBA Project Closing, Ethics, and Professional Responsibilities Purdue University Global Free custom sample in 24 to 48h

This GM594 Unit 9 ethics case analysis follows a county 911 district's projects manager asked to certify a grant completion date the project did not meet. Purdue Global GM 594, Project Closing, Ethics, and Professional Responsibilities, sets MS in Management students a closing dilemma to work through with a professional code. The state grant holds back $120,000 until the district certifies the backup power system was fully operational by November 30. Substantial completion came on November 20, but acceptance came on December 9. The executive director wants November 20 written. Read against the honesty standards in PMI's ethics code, the analysis judges that date a half-truth, weighs three options and chooses a full chronology with an advance request to the grant program.

CourseGM594 Project Closing, Ethics, and Professional Responsibilities
UnitUnit 9
Paper typeEthics case analysis
LengthAbout 1,110 words, 7 pages double-spaced
FormatAPA 7 student paper
SchoolPurdue University Global
ProgramMS in Management
UpdatedOctober 2026

Free sample paper for GM594 Unit 9

1

Fully Operational by November 30: A Unit 9 Ethics Case Analysis on a Grant Completion Date

[Student Name]

Purdue University Global

GM594: Project Closing, Ethics, and Professional Responsibilities

Unit 9 Ethics Case Analysis

[Instructor Name]

[Date]

The emergency communications district, its staff, the grant and every figure are composite and illustrative; the code and research cited are real.

What this part is doingStating the date, the request and the money in the lead puts the ethical tension in front of the reader at once.
2

The Facts

The Ridgeline Emergency Communications District received a $1.2 million state 911 grant toward its backup power and cooling upgrade. The grant agreement sets an end date of November 30 and holds back 10 percent, $120,000, until the district files a final report certifying that the funded system was fully operational by the end date.

The project reached substantial completion on November 20, when the new generator first carried the building and the architect certified the work as usable. But the first transfer test had failed, at 14 seconds against a 10-second requirement, and the alarm escalation to a second contact had never been configured. The transfer passed on retest on December 2, and the alarm escalation passed on December 9, which the district recorded as its acceptance date.

The executive director, preparing the report with the projects manager, asked her to write November 20 as the date the system became fully operational. The executive director's reasoning, as the case gives it: "The generator was running and carrying the building on the twentieth. Everything after that was fine-tuning. We are not going to lose $120,000 over a text message setting."

The Code

The projects manager is a certified project management professional and has agreed, as a condition of that certification, to follow PMI's ethics code. The code sets out four values, responsibility, respect, fairness and honesty, each with aspirational standards that practitioners strive for and mandatory standards they must follow (Project Management Institute, 2006). The mandatory honesty standards prohibit behavior meant to deceive, including making false or misleading statements, stating half-truths, giving information out of context, and withholding information that would make a statement misleading.

Testing November 20 Against the Code

Writing November 20 is not a plain falsehood. The generator did carry the building that day. But the grant asks when the system was fully operational, and on November 20 the system did not meet two of its own acceptance criteria. Writing November 20, with no explanation, would invite the grant program to believe the system met its criteria by the end date. That is a half-truth under the code: each word can be defended, but the statement as a whole is meant to leave a false impression.

November 20 is a true date put to a misleading use, which is exactly what the code means by a half-truth.

What this part is doingThe highlighted sentence states the analysis's central judgment in the code's own terms.
3

The executive director's framing matters too. Calling the alarm escalation a text message setting makes it sound minor. For a 911 center, an alarm that reaches one phone and stops is a real gap: an overnight generator fault could go unanswered. The acceptance criteria existed because the district decided at approval that the gap mattered.

Max Bazerman and Ann Tenbrunsel describe how people under pressure redefine a decision so that its ethical dimension fades, often by focusing on the business stakes and describing the troubling part in smaller terms (Bazerman & Tenbrunsel, 2011). Calling the criterion fine-tuning is an example.

Who Is Affected

Four groups have a stake in the date. The state grant program relies on final reports to decide whether public money bought what it was meant to buy, and other districts compete for the same funds. The county's residents depend on the center's backup power working as designed, including the alarm that would summon a technician at night. The district's board is responsible for the reserve that would cover a lost holdback and for the district's reputation with the state. And the projects manager's own professional standing rests on the reports she signs. The Project Management Institute frames project decisions as affecting stakeholders well beyond the project team, and asks practitioners to weigh those interests openly (Project Management Institute, 2021). Only the executive director's framing treats the date as a matter between the district and the grant program alone.

Three Options

Write November 20. Secures the $120,000 if the grant program does not inquire. Violates the mandatory honesty standard. If the program later reviews the acceptance record, which is a public document, the district risks repayment of more than the holdback and damage to its standing for future grants.

Write December 9 and accept the consequence. Honest. Risks losing the $120,000, which the district would have to cover from its reserve, already drawn down for the overrun.

Write December 9 with a full chronology, and ask the program in advance for a decision. Honest. Before filing, the projects manager calls the grant manager, explains that the system carried the building from November 20 and met all criteria on December 9, and asks whether the program will release the holdback, grant a short extension or release part of it. The report then states the facts and whatever the program decides.

The Decision

The projects manager should choose the third option. She should first tell the executive director, in person, that she cannot sign a report giving November 20 as the date the system was fully operational, and explain why with the code's words. She should then propose the call to the grant manager, offering to make it with the executive director. If the executive director refuses and asks someone else to sign, the code's responsibility standard requires the projects manager to raise the matter with the board chair.

She should keep a written record of each conversation, with dates, so that the sequence of her decisions can be shown later if the report is ever questioned. The costs are real. The district may lose some or all of the $120,000. The projects manager's relationship with the executive director may suffer. Against that, the district keeps its credibility with the grant program, avoids a statement that could later require repayment, and keeps the acceptance criteria meaningful for the next project.

Why Asking First Matters

The third option is not only the honest one; it is often the effective one. Grant programs frequently allow extensions when a project is substantially complete and the delay is documented. Asking before filing gives the program a chance to say yes, and it shows the district treating the grant's terms as a commitment rather than a hurdle. If the program refuses, the district has lost money but nothing else, and it can make a stronger case in its next application by pointing to a record of accurate reporting.

What this part is doingEnding on why asking first matters shows that honesty and the district's interests are not necessarily opposed.
4

References

Bazerman, M. H., & Tenbrunsel, A. E. (2011). Blind spots: Why we fail to do what's right and what to do about it. Princeton University Press.

Project Management Institute. (2006). PMI code of ethics and professional conduct.

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.).

GM594 Unit 9 instructions, in plain terms

GM594 Unit 9 asks you to analyze an ethical dilemma arising at a project's close. Set out the facts with dates and amounts, and quote or state the request at the center of the case. Describe the professional code you apply accurately, including its values and the difference between aspirational and mandatory standards. Test the proposed action against the code's specific language, and say whether it is a falsehood, a half-truth or acceptable. Notice how the request is framed, since pressure often works by making the ethical part sound minor. Identify who is affected beyond the people in the room. Weigh at least three options with their consequences, then choose one and set out the sequence of actions, including what to do if the request is repeated. State the costs honestly. Expect about seven pages, citing the code and research on ethical decision making in APA 7.

How the GM 594 Unit 9 example is put together

The facts give a $1.2 million grant, a November 30 end date and a $120,000 holdback, then November 20 substantial completion, a December 2 transfer retest and December 9 acceptance, and quote the executive director calling the alarm escalation a text message setting. PMI's code is described with its four values and mandatory honesty standards. November 20 is tested and judged a half-truth, as the highlighted sentence states. Bazerman and Tenbrunsel explain how calling a criterion fine-tuning makes the ethics fade. A section names the grant program, residents, the board and the projects manager as affected, citing the PMBOK guide. Three options are weighed: write November 20, write December 9 and accept the loss, or write December 9 with a chronology after calling the grant manager. The decision sets the sequence, including the board chair if someone else is asked to sign, and a written record of each step.

GM594 Unit 9 rubric: what earns full points

GM594 instructors look for an accurate reading of the code applied to the case's exact facts. Facts with dates and amounts earn early credit. Describing the code's structure correctly, including mandatory standards, shows understanding. Testing the proposed statement against the code's language, and naming it precisely as a half-truth or otherwise, carries significant weight. Recognizing how the request was framed shows insight into how pressure works. Identifying affected stakeholders widens the analysis. Weighing several options, choosing one and setting out a sequence of actions shows the analysis leads to conduct. Honest costs make the decision credible. PMI's Code of Ethics and Professional Conduct, Bazerman and Tenbrunsel's Blind Spots and the PMBOK Guide supply the citations in APA 7.

GM594 Unit 9 help from the desk

Many GM594 Unit 9 analyses quote the code's values in general terms without testing the specific statement against them. Others treat the choice as lying or telling the truth, missing the half-truth that the code addresses directly. A common gap is the option that protects both honesty and the organization, such as asking the funder first. Some writers stop at the analysis without saying what the professional will actually do. State the facts and the request, describe the code accurately, test the statement against its words, notice the framing, name who is affected, weigh options, decide, set out the steps and state the costs.

Get a GM594 Unit 9 example written to your instructions

Quote the Unit 9 case verbatim, say which ethics code or framework applies, and include the rubric. Facts, a fairly stated pressure, the standard described accurately, options on shared criteria and a decision with its sequence and personal cost form the analysis, in that order. First sample free; allow 24-48h. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.

More GM594 papers and MS in Management samples

GM594 Unit 9 questions, answered

Does applying the PMI code require membership?

No. The PMI Code of Ethics and Professional Conduct is published openly, and the paper applies it as a professional standard to a composite case. The sample notes that the code was written for PMI's members and volunteers while using it as the benchmark the course names. Accuracy matters more than affiliation: describe its structure correctly and quote it sparingly.

Is escalating to a supervisor enough?

Rarely, and the prompt usually makes it insufficient on purpose. Here the pressure comes from the executive director, so escalation has limits. The sample decides first, then informs, telling the director in writing what it will report and why. Escalation can be part of a decision; it cannot replace one, and graders usually separate the two.

What if the honest option harms the organization?

Then the paper should say how much and look for a route that limits the harm without the misstatement. The sample finds one: asking the grant officer for a no-cost extension before the report is due, which may protect the holdback. Where no such route exists, the analysis should still choose, and state the cost openly.

Where can I find a free GM594 Unit 9 sample paper?

This page carries a full GM594 Unit 9 ethics case analysis on a 911 district's grant completion date, applying PMI's code to a half-truth, with three options, a decision and APA 7 references.

Why is writing November 20 a half-truth?

The generator did carry the building that day, but the grant asks when the system was fully operational, and two acceptance criteria were not met until December 9. Writing November 20 without explanation would leave a false impression.