| Course | GB527 Global Operations |
|---|---|
| Unit | Unit 3 |
| Paper type | Capacity calculation |
| Length | About 910 words, 6 pages double-spaced |
| Format | APA 7 student paper |
| School | Purdue University Global |
| Program | MBA |
| Updated | October 2026 |
Free sample paper for GB527 Unit 3
From 686 Regulators on Paper to a 92-Unit Weekly Gap: A Unit 3 Capacity Calculation
[Student Name]
Purdue University Global
GB527: Global Operations
Unit 3 Capacity Calculation
[Instructor Name]
[Date]
The plant, its lathes and every figure are composite and illustrative; the sources cited are real.
The Cell
Platte Valve Works machines the bodies of its pressure regulators, which hold water pressure steady at the end of a pivot, in a cell of three CNC lathes. It works a weekday schedule of two shifts, each eight hours long. Each regulator body takes 21.0 machine-minutes. The plant manager has used the cell's design capacity in next year's plan, which assumes 560 regulators a week in peak months.
Table 1: Design Capacity
Machines: 3.
Hours per machine each week: 2 shifts of 8 hours, 5 days, or 80 hours.
Machine-hours each week: 240.
Machine-minutes per regulator: 21.0.
Design capacity: 240 times 60, divided by 21.0, or about 686 regulators a week.
Design capacity is what the cell could produce if it never stopped. No cell runs that way.
Table 2: Deductions to Effective Capacity
Breaks: 30 minutes a shift on each machine, about 15 machine-hours a week.
Planned maintenance: about 12 machine-hours a week.
Changeovers: about 16 changeovers a week across the three lathes, at 50 minutes each, or about 13.3 machine-hours.
Effective machine-hours: 240 less 15, 12 and 13.3, or about 199.7.
Effective capacity: 199.7 times 60, divided by 21.0, or about 570 regulators a week.
Effective capacity is what the cell can produce under planned conditions. Heizer et al. (2020) define it as design capacity less the allowances a process must make for its normal operation, such as maintenance and changeovers.
Table 3: Efficiency and Actual Output
Twelve weeks of production records show the cell producing an average of about 468 regulators a week. Against effective capacity of 570, that is an efficiency of 82 percent. The shortfall comes from unplanned stops: tool breakage, waiting for castings, minor breakdowns and quality holds.
Actual expected output: 570 times 0.82, or about 468 regulators a week.
Planned demand in peak months: 560.
Weekly gap: about 92 regulators.
The plan counts on 686 regulators a week, the cell can be expected to make 468, and the difference is not a surplus of 126 but a shortfall of 92.
Table 4: Ways to Close the Gap
1. Faster changeovers. Cutting changeover time from 50 to 25 minutes through standard tooling and preparing the next job while the lathe runs would add about 6.7 effective machine-hours a week, worth about 16 regulators at 82 percent efficiency. Cost: about $12,000 in tooling carts and training.
2. Higher efficiency. Raising efficiency from 82 to 88 percent by reducing tool breakage and casting shortages would add about 34 regulators a week. Cost: a tool-life program and a kanban for castings, about $15,000 a year.
3. A Saturday shift in peak months. One eight-hour shift on all three lathes, less breaks, adds about 22.5 machine-hours, worth about 57 regulators at 88 percent efficiency. Cost: overtime of about $2,900 a week.
4. A fourth lathe. A fourth machine would raise expected output to about 624 regulators a week at current efficiency. Cost: about $310,000 installed.
Why Changeovers Come First
Changeover time is the cheapest capacity the cell has. Womack and Jones (2003) describe the lean approach of separating changeover tasks that must be done with the machine stopped from those that can be done while it runs, and moving as many as possible into the second group. At Platte, operators now fetch tools, find the program and measure the first part only after the lathe stops. Preparing the next job's tools on a cart, loading the program in advance and using preset tool holders could halve the stop. Shorter changeovers also allow smaller batches, which helps the custom orders that make up a growing share of regulator demand and shortens the waiting that the Unit 1 post found throughout the plant.
Combining the Options
Faster changeovers and higher efficiency together would raise expected output to about 519 regulators a week, closing nearly half the gap at modest cost. Adding the Saturday shift in peak months would bring the cell to about 575, slightly above demand. The fourth lathe would close the gap alone but would sit underused outside peak months.
Hopp and Spearman (2011) caution that planning a cell to run close to its full capacity leaves no room for variability, which shows up as long queues and late orders. A cell planned at 575 against demand of 560 would run at about 97 percent of its expected output, so the plan should also build regulator stock in the weeks before peak months.
Recommendation
Start the changeover and efficiency programs now, so their gains are in place before the January peak. Schedule Saturday shifts from January through April. Build about 300 regulators of stock in November and December. Review the fourth lathe if demand grows beyond 600 regulators a week or if efficiency does not reach 88 percent within six months. Most important, correct the plan: capacity should be stated as expected output, not design capacity.
Limits
The calculation uses averages from twelve weeks, and changeover counts vary with the product mix. If demand shifts toward more custom regulators, changeovers will rise and effective capacity will fall. The efficiency figure also hides causes that differ week to week, which the efficiency program should track separately.
References
Heizer, J., Render, B., & Munson, C. (2020). Operations management: Sustainability and supply chain management (13th ed.). Pearson.
Hopp, W. J., & Spearman, M. L. (2011). Factory physics (3rd ed.). Waveland Press.
Womack, J. P., & Jones, D. T. (2003). Lean thinking: Banish waste and create wealth in your corporation (Rev. ed.). Free Press.
What the GB527 Unit 3 assignment asks for
In GB527 Unit 3 you calculate the capacity of an operation and compare it with demand. Set out the operation's machines, shifts and time per unit, and compute design capacity. Deduct planned losses such as breaks, maintenance and changeovers to reach effective capacity, showing each deduction. Apply measured efficiency from production records to estimate actual output. Compare the result with planned demand and state the gap. Then compare several ways to close it, with their effect on output and their cost, and recommend a combination. Note the limits of the calculation. Expect about four pages, most of them tables, citing operations sources in APA 7.
How this GB527 Unit 3 example is built
Table 1 sets out three lathes, two shifts, five days and 21.0 machine-minutes per regulator, for design capacity of about 686 a week. Table 2 deducts 15 hours of breaks, 12 of maintenance and 13.3 of changeovers to reach about 570, citing Heizer and colleagues on effective capacity. Table 3 applies twelve weeks of records showing 82 percent efficiency, giving about 468 against 560, and the highlighted sentence contrasts the planned surplus with the real shortfall. Table 4 costs faster changeovers, higher efficiency, Saturday shifts and a fourth lathe. A section on changeovers cites Womack and Jones. The combined plan reaches about 575, and Hopp and Spearman's caution about running near capacity supports building stock ahead of the peak.
Reading the GB527 Unit 3 grading rubric
GB527 instructors grade this calculation on each step from design capacity to expected output and on options compared with figures. Design capacity should be computed from machines, hours and time per unit. Each deduction should be shown, so the reader can check effective capacity. Applying measured efficiency to reach expected output carries significant weight, because it is the figure planning should use. Stating the gap against demand earns credit. Comparing options by their output and cost, and combining them, shows judgment. Noting that a plan close to full capacity needs a buffer shows awareness of variability. The calculation's APA 7 sources are the Heizer operations text, Hopp and Spearman and Womack and Jones on lean changeovers.
Common GB527 Unit 3 mistakes, and how to avoid them
Many GB527 Unit 3 calculations stop at design capacity or at effective capacity and treat it as what the operation will produce. Others deduct losses without showing the figures, so the reader cannot check them. A common gap is efficiency: unplanned stops reduce output below effective capacity, and measured records show by how much. Some writers recommend new equipment without trying cheaper options first. Compute design capacity, show each deduction, apply measured efficiency, state the gap, compare options by output and cost and plan a buffer for the peak. Correcting the planning figure itself, so future plans use expected output, is often the most valuable recommendation of all.
Get a GB527 Unit 3 example written to your instructions
Which operation needs analyzing? List its shifts, resources and time per unit if known, and include the Unit 3 prompt and grading rubric. Stepping from design to effective to expected capacity, the free first custom sample reports the gap on an honest basis within 24-48h. Where data is incomplete, each assumption is flagged so real figures can be swapped in. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.
More GB527 papers and MBA samples
- GB527 Unit 1: Discussion Board Post
- GB527 Unit 2: Process Analysis
- GB527 Unit 4: Quality Improvement Memo
- GB527 Unit 5: Inventory Model
- GB527 Unit 6: Seminar Reflection
- GB527 Unit 7: Supplier Comparison
- GB527 Unit 8: Network Design Analysis
- GB527 Unit 9: Demand Forecast
- GB527 Unit 10: Operations Report
- GB526 Unit 3: Case Analysis
- GB525 Unit 3: Trade Policy Analysis
- GB520 Unit 3: Workforce Planning Paper
- GB519 Unit 3: Break-Even Analysis
GB527 Unit 3 questions, answered
What is the difference between effective capacity and actual output?
Effective capacity is what the operation could produce after the losses it plans for, such as breaks, maintenance and changeovers. Actual output is what it did produce, after unplanned losses as well, including breakdowns, scrap and material shortages. Efficiency is the ratio between them, and it is the most honest predictor of what next year's schedule will yield.
Where do I get changeover and maintenance figures?
Production records, maintenance logs and conversations with supervisors are the usual sources at work. Without access, published industry ranges or a clearly labeled estimate work in many sections. State the figure and its source beside the calculation, since these allowances often decide whether a gap exists at all, and a reader will want to test them.
Should the answer recommend buying more equipment?
Only after cheaper options are measured. Graders tend to look for the sequence: reduce planned losses, raise efficiency, add time, then add equipment. If the gap survives the first three, the case for a new machine is much stronger and easier to defend. Include a rough cost for each option so the comparison is not only in units.
Where can I find a free GB527 Unit 3 sample paper?
This page carries a full GB527 Unit 3 capacity calculation for an irrigation valve maker's regulator cell, with design and effective capacity, efficiency, the weekly gap, four options and APA 7 references.
Why start with faster changeovers?
Changeover time is the cheapest capacity the cell has. Preparing tools and programs while the lathe runs could halve each stop, adding about 16 regulators a week for about $12,000, and shorter changeovers also allow smaller batches for custom orders.