| Course | MT382 Construction Cost Estimating |
|---|---|
| Unit | Unit 10 |
| Paper type | Detailed estimate package |
| Length | About 1,100 words, 6 pages double-spaced |
| Format | APA 7 student paper |
| School | Purdue University Global |
| Program | BS in Business Administration |
| Updated | October 2026 |
Free sample paper for MT382 Unit 10
A Class 2 Estimate a Reviewer Can Test: An MT382 Unit 10 Detailed Estimate Package for a Recreation Center
[Student Name]
Purdue University Global
MT382: Construction Cost Estimating
Unit 10 Detailed Estimate Package
[Instructor Name]
[Date]
The project, quantities, prices and quotes are composite; the classification, practices and sources cited are real.
Part One: The Summary
Direct cost totals 13,236,000 dollars across twenty divisions, or 344.69 per square foot of the 38,400-square-foot building. The four largest divisions account for 44.7 percent: HVAC at 1,604,000 dollars; thermal and moisture protection, which carries the insulated metal panels and roofing, at 1,512,000; metals at 1,508,000; and electrical at 1,286,000. Concrete follows at 1,186,000 and finishes at 1,019,508. Site work appears in two divisions, earthwork at 612,000 and utilities at 634,492, together equal to the leveled site subcontract.
The Twenty Divisions
The remaining divisions complete the summary: existing conditions at 48,000 dollars for survey and demolition of a former tennis court; masonry at 642,000; wood, plastics and composites at 214,000; openings at 698,000; specialties at 182,000; equipment, chiefly the community kitchen, at 296,000; conveying equipment for the elevator at 118,000; fire suppression at 268,000; plumbing at 742,000; communications at 146,000; electronic safety and security at 132,000; and exterior improvements, paving and landscaping, at 388,000. Each total is the sum of its detail sheet, and the summary shows each division's share of direct cost so a reviewer can spot one that looks out of proportion.
General Conditions by Month
General conditions are priced from a staffing and facilities plan rather than as a percentage. A project manager at half time, a full-time superintendent and assistant superintendent, a project engineer, the field office, temporary utilities, cleanup, safety and testing coordination total 88,400 dollars a month. Fifteen months, from mobilization to final completion, give 1,326,000 dollars. A month added to the schedule would add 88,400 dollars here, which is why general conditions are tied to the schedule rather than to the building cost.
Markups in a Printed Order
Markups are applied in a fixed, printed order, because each rests on a different base. General conditions, priced by month for a fifteen-month construction period, add 1,326,000 dollars. The contractor's fee, at 4.5 percent of direct cost plus general conditions, adds 655,290. Bond and insurance, at 1.8 percent of everything above, add 273,911. The construction subtotal is 15,491,201 dollars.
Design contingency has stepped down to 3 percent at construction documents, adding 464,736 dollars. Escalation, from the estimate's September 2027 price date to the October 2028 construction midpoint, thirteen months at the forecast 4.2 percent a year, is 4.56 percent, or 727,250 dollars. The owner's construction contingency, at 5 percent, adds 834,159. The total is 17,517,346 dollars.
Part Two: Detail by Division
Each division has its own detail sheet, and each line carries quantity, unit, labor, material and equipment rates and the extension. Labor, material and equipment sit in separate columns, so a reviewer can question the crew rate without touching the block price. The masonry sheet shows the labor rate built in Unit 5, 13.19 dollars per block, as a visible line beside block, mortar and grout material and scaffold equipment, rather than buried in a combined unit price. Holm et al. (2005) recommend exactly this separation, because combined unit prices hide which component is out of line when an estimate is questioned.
Where subcontractor quotes replace in-house pricing, the leveled figure is used and named. Site work, for example, is carried at 1,246,492 dollars, bidder B's leveled price from Unit 9, including its unit-price allowance at the geotechnical report's quantities. The detail sheet notes the rock sensitivity found in that analysis.
Every figure on the summary page can be followed to a detail line, and every detail line to a quantity, a rate and a source.
Part Three: Basis of Estimate
The basis of estimate follows the recommended practice for that document (AACE International, 2014) in content, if not in every heading. It lists the construction documents priced and their dates; the pricing sources, including the contractor's historical cost data and current supplier quotes; the subcontractor quotes used and how each was leveled; allowances, such as the rock and unsuitable soil quantities; assumptions, such as a single construction phase and normal working hours; and exclusions, such as land, design fees, furniture and equipment, and utility company charges.
Estimate Class
With construction documents essentially complete and most of the cost priced from takeoff or leveled quotes, the estimate is a Class 2 estimate under the building-industry classification (AACE International, 2020), with an expected accuracy range far narrower than at schematic design.
Reconciliation to Design Development
The package closes by reconciling to the May design development total of 17,083,915 dollars. The new total is higher by 433,431 dollars, or 2.54 percent. Direct cost rose as the drawings were completed and quotes replaced allowances, while design contingency fell from 6 to 3 percent. The reconciliation table lists each division's change and each allowance's change, so the board can see that the increase came from priced scope rather than from new contingency.
How to Test the Package
A reviewer can test the estimate at three levels. At the top, the summary's division totals and markups should add to 17,517,346 dollars. In the middle, any division total should equal the sum of its detail lines. At the bottom, any detail line should equal its quantity times its rates, with the quantity traceable to a takeoff sheet and the rate to a named source. A failure at any level points directly to where the problem lies.
Escalation Basis
The price date is September 2027, when the last supplier quotes were received. The construction midpoint, October 2028, comes from the contractor's preliminary schedule: a March 2028 notice to proceed and a fifteen-month construction period, with spending weighted toward the middle months. The 4.2 percent annual rate is the same published forecast used in the January memo, so the escalation line changes only because the months changed. If the bid slips, the escalation line should be recalculated before the budget is set; each month of delay adds roughly 57,000 dollars of escalation at the current base, before the construction contingency applied on top of it.
What Remains Uncertain
Even at Class 2, three uncertainties remain and are named: the quantity of rock, the final price of the switchgear and transformer, and the steel joist market, which rose 11 percent between January and May. Each is covered by the construction contingency rather than added to the direct cost, and each will be reported against that reserve if it materializes.
References
AACE International. (2014). Basis of estimate (Recommended Practice No. 34R-05). AACE International.
AACE International. (2020). Cost estimate classification system: As applied for the building and general construction industries (Recommended Practice No. 56R-08). AACE International.
Holm, L., Schaufelberger, J. E., Griffin, D., & Cole, T. (2005). Construction cost estimating: Process and practices. Pearson Prentice Hall.
MT382 Unit 10 instructions, in plain terms
The final unit asks students to assemble a detailed estimate package at the construction documents stage. The package should include a summary by division, detail sheets with quantities and separate labor, material and equipment rates, a markup sequence, and a basis of estimate. Instructors expect earlier course work, such as productivity rates and leveled subcontractor prices, to appear by name in the detail. The basis of estimate should list documents, sources, quotes, allowances, assumptions and exclusions. Escalation and contingencies should be recalculated for the current stage. The package should reconcile to the previous estimate and state its class. Remaining uncertainties should be named rather than hidden in unit prices.
How the MT 382 Unit 10 example is put together
This sample's summary page gives the four largest divisions and their share, then completes the list of twenty. General conditions are built from a monthly staffing and facilities plan. Markups are applied in a printed order with each base named. The detail section explains the separation of labor, material and equipment, citing Holm and colleagues, under a highlighted line about following every figure to a source. Site work uses the leveled bid by name. The basis of estimate follows AACE's practice for that document, the class is stated, escalation is dated, and the reconciliation to design development explains the 2.54 percent increase. A section shows how to test the package at three levels, and uncertainties close it.
MT382 Unit 10 rubric: what earns full points
Detailed estimate packages tend to be graded on completeness, traceability, correct markups and the quality of the basis of estimate. A summary that adds exactly to the total, with division detail that supports each line, earns the core marks. Rubrics reward labor, material and equipment shown separately, with earlier work carried forward visibly. Markups applied in a stated order to stated bases show technical care. A basis of estimate that would let another estimator understand every assumption demonstrates professionalism. Reconciliation to the prior estimate shows control. Naming remaining uncertainties shows honesty. AACE's two recommended practices and the course text are cited in APA 7, and the package reads as a document an owner's reviewer could audit without calling the estimator.
MT382 Unit 10 help from the desk
Final packages often present a long list of line items with no summary, or a summary with no detail behind it. Combined unit prices hide which component drives cost. Markups are sometimes applied to the wrong base or in an order that changes the total. The basis of estimate is frequently a short paragraph instead of a full record of sources and assumptions. Reconciliation to the earlier estimate is often skipped, leaving the reviewer to wonder why the total changed. Before submitting, pick one line on the summary and follow it down to a quantity and a rate. If the trail breaks anywhere, fix it before a reviewer finds it.
Get an MT382 Unit 10 example written to your instructions
For the Unit 10 package, the inputs are the construction documents or scope, any quantities, rates or quotes carried from earlier units, and the rubric. Expect the first complete package free in 24-48h: a division summary, detail sheets splitting labor, material and equipment, a printed markup order, and a basis of estimate naming assumptions and exclusions. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.
More MT382 papers and BS in Business Administration samples
- MT382 Unit 1: Early Cost Number Anchoring Post
- MT382 Unit 2: Conceptual Cost Estimate
- MT382 Unit 3: Cost Index Location and Time Adjustment
- MT382 Unit 4: Exterior Wall Assemblies Estimate
- MT382 Unit 5: Masonry Labor Productivity Analysis
- MT382 Unit 6: Estimate Contingency Seminar Reflection
- MT382 Unit 7: Contingency and Escalation Memo
- MT382 Unit 8: Estimate Reconciliation Bridge
- MT382 Unit 9: Site Work Bid Leveling
- MT381 Unit 10: Baseline Schedule Submittal
- MT362 Unit 10: AI Adoption Proposal
- MT361 Unit 10: Fourplex Property Management Plan
- MT359 Unit 10: Integrated Campaign Plan
MT382 Unit 10 questions, answered
What goes in a basis of estimate?
A written description of how the estimate was built: the documents and their dates, the estimate class, pricing sources, subcontractor quotes, allowances, assumptions, exclusions, contingency and escalation, and how the figure compares with the previous estimate. AACE International publishes a recommended practice for it. The document lets a reviewer challenge premises instead of guessing at them.
Why separate labor, material and equipment?
Because each behaves differently. Labor varies with productivity and wage rates, material with market prices and waste, equipment with duration and utilization. Separating them lets a reviewer check each rate against its source, and lets the estimate be adjusted when one input changes without rebuilding the line.
How much contingency belongs in a detailed estimate?
Less than earlier, because most design is complete. Design contingency often falls to a few percent at construction documents, while an owner's construction contingency for field conditions and changes usually remains. State each separately, with its purpose, and follow any percentages your course or owner prescribes.
Where can I find a free MT382 Unit 10 sample paper?
This page has the full MT382 Unit 10 detailed estimate package, a Class 2 estimate of 17,517,346 dollars for a recreation center.
How does the MT382 Unit 10 sample reconcile to design development?
The total rose 433,431 dollars, or 2.54 percent, because direct cost grew as drawings were completed while design contingency fell from 6 to 3 percent.