Behind on Billing, Two Days Behind on the Finish: A Unit 10 Project Management Report on Station 2 at Month Seven
[Student Name]
Purdue University Global
MT281: Fundamentals of Construction Management
Unit 10 Project Management Report
[Instructor Name]
[Date]
Station 2, its contract, schedule, costs, people and decisions are composite and illustrative and draw on the earlier units' samples; the sources cited are real.
Summary for the Board
Station 2 is at working day 150 of a contract now set at 239 days. The forecast finish is day 241, two days late, because of rework the contractor caused and must absorb. Work completed is valued at $3,779,993, which is 5.5 percent below the $4,000,000 the schedule planned to bill by now, but most of the gap is timing in the noncritical bay work, not a threat to the finish. The revised contract sum is $6,461,526 after two approved change orders. There have been no lost-time injuries. The board is asked for three decisions, listed at the end.
Schedule Status
The critical path at day 150 runs through the living wing's interior finishes, which started on day 151 after insulation and drywall; the wing rough-in and its inspection are complete. The original contract time of 232 working days has been extended twice, to 239, by change orders issued under the general conditions (American Institute of Architects [AIA], 2017).
The delay log lists every event that has affected the schedule.
Concealed soil under the bay: 4 days; excusable and compensable under Section 3.7.4 of the general conditions; extension granted
Rain beyond the allowance during the bay undercut: 3 days; excusable, not compensable; extension granted
Drains in the wing set high and reset: 2 days; contractor's responsibility under Section 12.2; no extension
Joist delivery 19 days late: absorbed by float; no effect on the finish
Door lintel answer 6 days late: absorbed by float; no effect on the finish
The forecast of day 241 is the revised contract time of 239 plus the 2 days of drain rework. The contractor has proposed Saturday drywall shifts at its own cost to recover them, which would bring the forecast back to day 239. Trauner et al. (2009) stress that a delay log should classify each event by cause and by effect on completion, so that owners can see which days they owe and which they do not, and this log does both.
Cost Status
Original contract sum: $6,373,900
Change order 1, concealed soil: $26,096
Change order 2, larger generator: $61,530
Revised contract sum: $6,461,526
Work completed to date: $3,779,993
Retainage held at 5 percent: $189,000
Paid to date, net of retainage: $3,590,993
The 5.5 percent gap between planned and actual billing has two causes. The bay's sequence, which carries some of the project's highest-cost items, the sectional doors, exhaust system and gear lockers, has 23 days of float in the baseline and is running about two weeks behind its early dates while staying within that float. And the generator, a $61,530 item, will be billed when it is delivered and set, which falls after this report. Neither cause affects the finish date. Halpin et al. (2017) note that billing progress and schedule progress often diverge when high-cost noncritical work runs later than its early dates, which is why both must be reported.
The money is behind where the plan expected it; the finish date is not.
Change Log
One change is pending. Change request 3, reinforcement at the bay roof joists for the vehicle exhaust rail hangers, $9,450, addresses the coordination gap found in the document review. The joist supplier has confirmed the added hanger loads require bridging reinforcement at six joists. The architect recommends approval.
Safety
There have been no lost-time injuries. The masonry limited access zone at the fire wall was maintained as planned, and the fire wall was completed before wing slab work began, as the safety plan required. One near miss was recorded: a skid steer reversed toward a laborer near the bay undercut; the contractor added a spotter rule for reversing equipment.
Quality
All concrete cylinder tests for the slabs, footings and walls have met the specified strengths. The first set of apron cylinders, specified at 4,500 psi air-entrained, will be tested next week. Compaction tests for the bay undercut fill all passed.
Risks for the Next Quarter
Three risks are being watched. The sectional doors' float, 8 days in the baseline, now stands at 2 after the late lintel answer, so any delivery slip will reach the finish. The interior finishes are the longest critical activity, 40 days, and depend on tile and flooring deliveries that the contractor has confirmed in writing. And the final inspection depends on the fire marshal's schedule, which the township has asked to reserve for the week beginning on day 208.
Fifteen-Day Look-Ahead
Wing interior finishes continue. Bay mechanical and exhaust work starts on day 156. The sectional doors are scheduled for delivery on day 152 and installation from day 153. The generator is scheduled for delivery on day 158.
Decisions Requested
1. Approve change request 3, exhaust hanger reinforcement, $9,450, from the township's construction contingency, by the next meeting, so the joist reinforcement can be installed before the exhaust rails.
2. Confirm the fire chief's gear locker layout by day 160, so the lockers can be ordered within their remaining float.
3. Set the station's dedication date no earlier than four weeks after the forecast finish, to allow for the punch list and move-in.
References
American Institute of Architects. (2017). AIA document A201-2017: General conditions of the contract for construction. American Institute of Architects.
Halpin, D. W., Lucko, G., & Senior, B. A. (2017). Construction management (5th ed.). Wiley.
Trauner, T. J., Manginelli, W. A., Lowe, J. S., Nagata, M. F., & Furniss, B. J. (2009). Construction delays: Understanding them clearly, analyzing them correctly (2nd ed.). Butterworth-Heinemann.
Reading the MT 281 Unit 10 instructions
Unit 10 closes the course with a status report for the owner's governing body that puts schedule, cost and cause on the same pages. Begin with a one-page summary the board could read alone. Report schedule status with the critical path, the current contract time and the forecast, and list every delay with its cause, classification and effect. Report cost status from original contract to revised sum, work completed and retainage, and explain any gap between billing progress and schedule progress. Include changes pending, safety, quality, risks and a short look-ahead. End with decisions the board must make, each with a deadline. Nine pages under a summary, drawing on the earlier units, is a typical format.
How this MT281 Unit 10 example is built
The report opens with a board summary covering the day, the forecast, the billing gap, the contract sum and three decisions. Schedule status names the critical activity and lists five delays with their classifications, citing the general conditions and Trauner and colleagues, under a margin note on showing delays that had no effect. Cost status traces the contract from $6,373,900 through two change orders to retainage and net payment. A section explains the billing gap with Halpin and colleagues, and the highlighted line separates money from the finish date. The change log, safety, quality, risks for the next quarter and a fifteen-day look-ahead follow. Three decisions with deadlines close it, under a final note.
MT281 Unit 10 rubric: what earns full points
Project management reports are graded on clarity for a non-technical board, accuracy and consistency of figures, honest treatment of delays and costs, and decisions that can be acted on. A summary that stands alone earns significant credit. Instructors reward delay logs that classify every event by cause and effect, including those that did not move the finish. Explaining why billing and schedule progress diverge shows real understanding of project controls. Figures must reconcile from original contract to revised sum and payments. Safety, quality and risk sections show a complete view. Decisions with deadlines make the report a management tool rather than a record, and accurate citations complete the rubric. A risk section for the next quarter shows the writer is looking ahead, not only reporting.
MT281 Unit 10 help from the desk
Reports most often fall short by describing a month's work without ever saying where the finish date and the contract sum now stand. Another frequent problem is figures that do not reconcile, such as a revised contract sum that does not equal the original plus approved changes. Some reports omit delays the owner caused, which undermines trust. Others end without asking the board for anything. Check every total against the earlier units, and make sure the forecast finish equals the contract time plus any delays the contractor carries. Send your project's current figures and delays, and a writer can draft the summary, reconcile the cost status and frame the decisions for the board.
Get an MT281 Unit 10 example written to your instructions
Bring the project status your Unit 10 prompt describes, including its schedule, cost figures and change records, plus the instructions and rubric, and say who will read the report. A first report is free in 24-48h, reconciling schedule with cost, classifying every delay, and ending with the decisions it needs. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.
More MT281 papers and BS in Business Administration samples
- MT281 Unit 1: Discussion Board Post
- MT281 Unit 2: Delivery Method Comparison
- MT281 Unit 3: Drawing and Specification Review
- MT281 Unit 4: Quantity Takeoff
- MT281 Unit 5: Construction Schedule
- MT281 Unit 6: Seminar Reflection
- MT281 Unit 7: Cost Estimate
- MT281 Unit 8: Change Order Analysis
- MT281 Unit 9: Site Safety Plan
- MT262 Unit 10: Global Team Leadership Plan
- MT260 Unit 10: Group Analysis Paper
- MT247 Unit 10: Adoption Assessment
- MT246 Unit 10: Change Request Package
MT281 Unit 10 questions, answered
How can a project be behind on cost progress but not on time?
When planned progress assumes early start dates and some work is legitimately running later within its float. Billing falls behind the plan while the critical path holds. A report should reconcile the two rather than present both as bad news. The sample measures progress against late dates as well, which shows the gap is float in use.
Should a report include delays the owner caused?
Yes, classified as such. A report that lists only the contractor's delays, or only the owner's, cannot be trusted by either party. Each event belongs in the log with its cause, days, classification and the contract basis for any extension. The board needs that record to understand why the contract finish moved.
What decisions belong at the end of the report?
Anything the audience must approve or confirm for work to proceed: pending change orders, test or inspection dates only the owner can set, and acceptance of recovery plans. State each as a yes-or-no question with its deadline. A report that asks for nothing leaves the reader unsure whether anything needs attention.
Where can I find a free MT281 Unit 10 sample paper?
This page carries the complete MT281 Unit 10 project management report. It reports a fire station's schedule, cost, delays, changes, safety and quality at day 150 and asks the township's board for three decisions.
How can Station 2 be behind on billing but nearly on time in the MT281 Unit 10 sample?
The billing gap comes from high-cost bay work running late within its float and from the generator, which bills on delivery. Neither is on the critical path, so the finish forecast moves only by the two days of drain rework.