MT237 Unit 10 Supply Chain Report Example

Reviewed by Chester Goodwin, MBA Supply Chain Systems Purdue University Global Free custom sample in 24 to 48h

The MT237 Unit 10 supply chain report on this page chooses one fix for a composite Kansas City desk maker: paying for visibility into lift-column shipments from Penang. Purdue Global MT 237 closes with a report, and the sample explains why this link was chosen over the stock feed, the pickup cap and others from earlier units. Its diagnosis reuses the Unit 5 split, in which arrival uncertainty drives about 1,498 sets of the uncertainty behind about 3,690 sets of safety stock. A service linking supplier, forwarder and carrier would cost about $30,000 in year one, cut safety stock by about 1,730 sets, avoid emergency air freight and save planner time, about $80,100 a year, for a first-year net of about $50,100. Alternatives, a spring rollout and five measures follow, drawing on Cachon and Fisher, Lee and Whang and Christopher and Peck for the BS in Business Administration.

CourseMT237 Supply Chain Systems
UnitUnit 10
Paper typeSupply chain report
LengthAbout 1,120 words, 7 pages double-spaced
FormatAPA 7 student paper
SchoolPurdue University Global
ProgramBS in Business Administration
UpdatedOctober 2026

Free sample paper for MT237 Unit 10

1

Nine Weeks of Silence From Penang: A Unit 10 Supply Chain Report on Paying for Shipment Visibility

[Student Name]

Purdue University Global

MT237: Supply Chain Systems

Unit 10 Supply Chain Report

[Instructor Name]

[Date]

Prairie Rise Desk Co., its suppliers, the visibility service and every cost and saving are composite and illustrative; bracketed figures stand where quotes and records would supply the numbers; the sources cited are real.

What this part is doingNaming the stock held and the net gain in the lead tells the owner what the report will defend.
2

Summary

Prairie Rise Desk Co. should subscribe to a shipment visibility service that links its supplier in Penang, its freight forwarder and the ocean carrier, so the planning system receives a confirmed ship date, sailing and arrival estimate for every container. The service costs about [$18,000] a year plus about [$12,000] to set up. It should allow lift-column safety stock to fall by about 1,730 sets, avoid most emergency air shipments and cut the planner's time spent chasing dates, saving about [$80,100] in the first year.

Why This Link

The term's earlier work examined seven parts of the chain. The two-layer map in Unit 2 found the Penang leg reported mostly by email. The information flow analysis in Unit 3 found the retailer's daily stock feed too slow, a problem that costs about [$25,000] a year and can be fixed for under [$2,000]. The vulnerability assessment in Unit 4 found the parcel pickup cap and the column stock the thinnest links in January. The inventory calculation in Unit 5 found lead-time uncertainty responsible for most column safety stock. The supplier comparison in Unit 7 kept Tulsa for frames. The transport study in Unit 8 proposed a linehaul test. The disruption plan in Unit 9 showed how much depends on knowing what is at sea.

The column link was chosen because it is the most expensive problem that information alone could solve. The stock feed fix is cheaper but smaller, and should be done regardless. The pickup cap is a contract term, not an information problem.

Diagnosis

Prairie Rise orders lift columns every four weeks with a nine-week average lead time. In practice a container can land a week and a half early or late without anyone being surprised. The Unit 5 calculation showed that late or early ships account for about 1,498 sets of the uncertainty Prairie Rise must cover over thirteen weeks, against 757 from shifts in demand, and that the cost-minimizing safety stock is about 3,690 sets at a 98.6 percent cycle service level, costing about [$95,700] a year to carry.

The variation itself cannot be removed, since sailings and ports are beyond Prairie Rise's control. What can change is when Prairie Rise learns about it. Today the company learns that a container is late only when the forwarder's arrival notice comes, often a week before the ship docks, or when the ship simply does not arrive. Lee and Whang (2000) argued that much of the cost of uncertainty in a chain comes from information arriving too late for anyone to act on it.

What this part is doingSeparating the delay that cannot be fixed from the late knowledge that can is the core of the diagnosis.
3

The Proposal

The visibility service connects to the supplier's packing records, the forwarder's booking system and the ocean carrier's vessel tracking. When the supplier packs a container, the service records it. When the container is booked, loaded and sails, the service updates the planning system automatically, with a revised arrival estimate whenever the vessel's schedule changes. A planner sees a slipping container weeks earlier than today and can react by moving the next order forward, booking a faster sailing or rationing stock before running out.

Cachon and Fisher (2000) showed that data is worth sharing only to the extent it alters what managers do, and here it changes three: how much safety stock to hold, when to place the next order and whether to expedite.

Alternatives Considered

Two alternatives were weighed. Moving column production closer, to the Taiwanese maker qualified last year or to a Mexican supplier, would shorten the lead time itself but at a higher unit price, about [$9] a set more, which on [48,700] sets a year would cost far more than the visibility service. Asking the Penang supplier to hold a consignment stock in a Kansas City warehouse would move the carrying cost onto the supplier, but the supplier declined when asked last year and would price the cost back into the columns. Visibility is the cheapest way to act on the problem without changing suppliers.

Costs

The service costs about [$18,000] a year for the expected number of containers and about [$12,000] to connect to the planning system and train the supplier's shipping clerk, for about [$30,000] in the first year and [$18,000] after.

Savings

If the visibility narrows the effective lead-time uncertainty from about 1.6 weeks to about 0.5, the Unit 5 calculation gives a safety stock of about 1,960 sets at the same service level, a reduction of about 1,730 sets. At a carrying cost of about [$25.96] a set, that saves about [$45,000] a year, and frees about [$204,000] of cash once, as stock runs down. Earlier warnings should also avoid most emergency air shipments of columns, which cost about [$20,000] last year. And the planner currently spends about six hours a week chasing dates by email and phone, about [$15,100] a year in time that could go to planning. Total yearly savings are about [$80,100].

The first-year net gain is about [$50,100], rising to about [$62,100] a year after setup.

The ships will not sail any faster; Prairie Rise will simply know weeks sooner when they are late.

Implementation

In the first month, Prairie Rise selects the service, signs the forwarder and carrier connections and agrees with the supplier on which packing data it will share. In the second month, the service runs alongside the current email process, and the planner compares arrival estimates with actual arrivals. In the third month, if the estimates are reliable, the planner begins lowering safety stock in steps of about [500] sets per container, watching for shortages. The full reduction is reached over about four months.

Risks

The supplier may be slow to share packing data, which would leave the first leg blind. The visibility estimates may be wrong for some sailings. And reducing stock before the January peak would be risky. The rollout should therefore start in spring, after the peak, and the stock reduction should pause each December until January's containers are confirmed.

Measures

Five measures will track the result: the accuracy of arrival estimates, measured as the average gap between estimated and actual arrival; lift-column safety stock in sets; stockouts of columns; emergency air shipments; and planner hours spent chasing dates. Christopher and Peck (2004) describe visibility as a foundation of resilience, and a year of these figures will tell Prairie Rise whether the subscription earned its place.

What this part is doingStarting after the peak and pausing each December shows the plan respects the risk it is trying to reduce.
4

References

Cachon, G. P., & Fisher, M. (2000). Supply chain inventory management and the value of shared information. Management Science, 46(8), 1032-1048. https://doi.org/10.1287/mnsc.46.8.1032.12029

Christopher, M., & Peck, H. (2004). Building the resilient supply chain. The International Journal of Logistics Management, 15(2), 1-14. https://doi.org/10.1108/09574090410700275

Lee, H. L., & Whang, S. (2000). Information sharing in a supply chain. International Journal of Manufacturing Technology and Management, 1(1), 79-93. https://doi.org/10.1504/IJMTM.2000.001329

The Purdue Global MT237 Unit 10 instructions

Unit 10 usually asks for a final supply chain report that chooses one problem from the term's work and proposes a fix. Start with a summary of the choice, cost and benefit. Explain why this link was chosen over others, condensing each earlier unit to a sentence or two. Diagnose the problem with numbers carried forward from earlier units, and separate what can be changed from what cannot. Describe the proposal concretely, including which partners must cooperate. Weigh at least one alternative. Itemize costs and savings, compute the net effect and state a conservative case if your section asks for one. A phased rollout that avoids the busiest season, risks with responses and measures tied to the diagnosis complete the report. Expect about nine pages with earlier tables in appendices, citing information and resilience research in APA 7.

How this MT237 Unit 10 example is built

The report opens with a summary of the visibility service, its cost and its savings. The choice section condenses seven earlier units and explains why the column link wins. The diagnosis carries forward the Unit 5 numbers and separates late ships, which cannot be prevented, from late knowledge, which can, with Lee and Whang on information arriving too late and a margin note on that distinction. The proposal explains how the service connects supplier, forwarder and carrier, citing Cachon and Fisher on information that changes decisions. Two alternatives, a nearer supplier and supplier-held consignment stock, are rejected on cost. After the itemized costs and savings, the highlighted line concedes that the ships will not sail any faster. Implementation starts in spring and pauses each December, with a second note, and risks and five measures close with Christopher and Peck.

Where the points sit in the MT237 Unit 10 rubric

The MT 237 capstone report rises or falls on three things: why this link was picked, how well the diagnosis is measured and whether the dollars are believable. Explaining why one link was chosen over others shows the writer weighed the term's findings. Carrying numbers forward from earlier units, rather than inventing new ones, earns credit for consistency. Separating causes the company can change from those it cannot shows clear thinking. Alternatives should be priced and rejected for stated reasons. Costs and savings must be itemized, with the net effect computed for the first year and after. A rollout that respects seasonal risk and measures that match the diagnosis make the report usable. Cachon and Fisher, Lee and Whang and Christopher and Peck should be cited.

Common MT237 Unit 10 mistakes, and how to avoid them

Final reports often lose points by trying to fix every problem found during the term. Another frequent issue is a proposal whose savings rest on figures that contradict earlier units. Some writers recommend a technology without explaining how it changes decisions. Others skip alternatives or the cooperation needed from partners. Costs may omit setup or training. Rollouts sometimes start at the worst time of year. Measures are often generic rather than tied to the problem. Earlier unit tables belong at the back, with a sentence or two about each up front. Bring your earlier unit papers and the figures they produced, and we can help choose the link, carry the numbers forward and build the case.

Get an MT237 Unit 10 example written to your instructions

Gather the earlier MT237 work the Unit 10 report draws on, or the assigned case, and send it with the rubric. One link diagnosed and one fix priced, with an expected and a cautious case, returns in 24-48h, and the first custom report costs nothing. Figures that changed during the term are reconciled openly. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.

More MT237 papers and BS in Business Administration samples

MT237 Unit 10 questions, answered

How should a final report choose which problem to fix?

By comparing the candidates on what each costs, what fixing it would save and what it would take, then choosing the one with the strongest case. Problems already solved cheaply should be named and set aside rather than ignored. The example explains in its overview why the supplier-visibility link remained after two smaller fixes were adopted during the term.

What is supply chain visibility?

The ability to see where goods and orders are, and when they will arrive, as events happen rather than after they surprise someone. It usually depends on partners sending electronic notices and on tracking data from carriers. Its value is indirect: it lets a firm hold less buffer stock and react earlier, which is why the example prices it through inventory and expediting savings.

Does the report need both an expected and a conservative case?

Many rubrics reward it, because savings estimates carry uncertainty and a reader wants to know whether the proposal survives if things go worse. The example's conservative case assumes less stock reduction and fewer avoided expedites and still stays positive. If the conservative case turned negative, the report would need to say so and argue why the risk is worth taking.

Where can I find a free MT237 Unit 10 sample paper?

This page carries a complete MT237 Unit 10 supply chain report on shipment visibility for lift columns from Penang. It explains the choice, diagnoses safety stock, prices the service, weighs alternatives and sets a rollout and measures, with margin notes.

How does visibility reduce safety stock if the ships are no faster?

It narrows the uncertainty the planner faces from about 1.6 weeks to about half a week by showing delays as they happen, so the company can react early and hold about 1,730 fewer sets at the same service level.