HA520 Unit 10 Comprehensive Financial Analysis Example

Reviewed by Chester Goodwin, MBA Health Care Financial Management Purdue University Global Free custom sample in 24 to 48h

This HA520 Unit 10 comprehensive financial analysis asks whether a composite 186-bed nonprofit hospital can afford an $85 million bed tower while its operating margin slides from 6.1 to 1.7 percent. It was written for Purdue Global HA 520, Health Care Financial Management, in the Master of Health Administration (MHA). Addressed to the board finance committee with its recommendation first, it carries three years of results, a ratio dashboard, payer and receivables risks and a borrowing pro forma. Every covenant holds after borrowing $60 million, but new depreciation and interest of about $5.43 million would nearly erase operating income. The committee is asked to defer twelve months and meet two targets.

CourseHA520 Health Care Financial Management
UnitUnit 10
Paper typeComprehensive financial analysis
LengthAbout 1,100 words, 7 pages double-spaced
FormatAPA 7 student paper
SchoolPurdue University Global
ProgramMaster of Health Administration (MHA)
UpdatedOctober 2026

Free sample paper for HA520 Unit 10

1

Not Yet, and Here Is What Would Change the Answer: A Comprehensive Financial Analysis for a Composite 186-Bed Nonprofit Hospital's Board Finance Committee on an Eighty-Five Million Dollar Bed Tower, Carrying Three Years of Results, Ratio Trends, Payer Exposure and a Borrowing Pro Forma Into One Recommendation

[Student Name]

Purdue University Global

HA520: Health Care Financial Management

Unit 10 Comprehensive Financial Analysis

[Instructor Name]

[Date]

The hospital, the project and every figure are composite and bracketed, drawing together the term's earlier analyses; the report is a course model, not financial advice.

What this part is doingThe report puts its conclusion first, because a finance committee reads the summary and consults the rest.
2

Summary for the Committee

Recommendation: defer final approval of the bed tower for twelve months. Proceed with design work. Approve construction if, over the next four quarters, the operating margin returns to at least [3] percent and days in accounts receivable fall to [47] or below. Reason: the hospital can borrow for the tower without breaching covenants, but the added depreciation and interest would nearly erase current operating income, leaving almost no room for further deterioration in payer mix or labor costs.

Historical Performance

Operating revenue: [$296.4], [$312.0] and [$327.0] million over three years. Operating income: [$17.1], [$19.1] and [$5.5] million. Operating margin: [5.8], [6.1] and [1.7] percent. The last year's decline came from expenses rising about twice as fast as revenue, led by agency staffing and supplies (Unit 2). Nonoperating gains of [$9.8] million held the bottom line above zero, but that cushion sits outside operations.

Ratio Dashboard

Liquidity: days cash on hand [191.0], above the peer median; days in receivables [52.5], worse than peers. Coverage: debt service coverage [3.46] times, down from [4.39]. Debt: debt to capitalization [34.0] percent. Plant: average age [13.9] years, older than peers, which supports the case for new beds (Unit 3). Indicators of this kind, tracked over time, are among the best early warnings of financial distress for hospitals (Pink et al., 2006).

Risks

Payer mix: a modest drift from commercial to Medicare Advantage and from Medicaid to self-pay could cut net revenue by about [$10.3] million (Unit 5). Receivables: [$6.4] million of cash sits in excess receivables (Unit 9). Labor: agency costs remain high and could rise again. National research on hospital profitability links a larger Medicare share and higher spending per discharge with weaker patient care profits (Bai & Anderson, 2016), and this hospital is drifting toward both. The tower is affordable under today's covenants but not under today's operations, and the gap between those two statements is the reason to wait.

The Pro Forma

Financing: borrow [$60] million at [5] percent over thirty years, adding about [$3.90] million of annual debt service; spend [$25] million of reserves. Debt service coverage: [3.46] falls to [2.57] times, above a typical covenant floor. Days cash on hand: [191.0] falls to [160.9]. Debt to capitalization: rises to [43.2] percent. Every covenant holds. Income effect: new depreciation of about [$2.43] million a year, over a [35]-year life, and first-year interest of about [$3.0] million add [$5.43] million of expense, nearly erasing the [$5.5] million of current operating income.

What this part is doingThe pro forma separates covenant compliance from operating effect, which is where the recommendation comes from.
3

What New Beds Would Bring

The tower would add [48] private rooms and replace [40] semi-private beds, raising capacity and patient experience. If volume grows [four] percent and the payer mix holds, incremental operating income could reach [$4] million a year by year three, offsetting most of the new expense. But that volume is uncertain, and the payer mix is moving the wrong way.

How the Term's Analyses Fit Together

Each earlier analysis points to the same conclusion from a different angle. The statements showed expenses outrunning revenue; the ratios showed a strong balance sheet and weakening operations; the payer mix analysis showed revenue at risk; the budget and variance work showed where costs drift; the capital evaluation showed how sensitive a large project is to volume; and the revenue cycle review showed cash waiting to be collected. Together they say the hospital's constraint is operating performance, not borrowing capacity.

Options

1. Approve now: highest risk; operating losses likely if trends continue.

2. Defer twelve months with targets: proceed with design, preserve the option, require operational recovery first.

3. Reduce scope: build [30] beds in phase one for about [$55] million.

4. Cancel: avoids risk but leaves an aging plant.

Health care finance texts emphasize that capital capacity depends on operating cash flow as well as on balance sheet strength (Cleverley & Cleverley, 2018), which favors option 2 or 3.

The Two Targets

1. Operating margin at or above [3] percent for four consecutive quarters, achieved by reducing agency staffing and controlling supply costs.

2. Days in accounts receivable at or below [47], achieved through the revenue cycle improvements in Unit 9.

Meeting both would add roughly [$4.3] million to annual operating income and release about [$4.7] million of cash, restoring the room the tower needs.

What Management Must Do in the Next Twelve Months

1. Cut agency spending by half through recruitment and retention.

2. Implement real-time eligibility checks and a denial prevention team.

3. Renegotiate Medicare Advantage contracts with clearer authorization terms.

4. Report progress on both targets to the committee quarterly.

Questions Board Members Are Likely to Ask

Why not borrow while rates are reasonable? Because the cost of the tower is not only interest; depreciation and operating costs of new space would arrive whatever the rate, and operations cannot absorb them yet. Will construction costs rise if we wait? Probably, by about [four] to [five] percent a year. A year's delay may add [$3] to [$4] million, which is less than one year of the operating losses the tower could cause if approved now. Are we losing patients to competitors because of old rooms? Some, mostly in obstetrics and orthopedics; the design phase can test whether a smaller first phase addresses those service lines.

What this part is doingAnticipating the board's questions shows that deferral was weighed against its costs, not chosen by default.
4

Community Considerations

The hospital is the only one in its county with intensive care. Its financial stability matters to the community more than any single building. Approving a project that weakens operations could put existing services at risk; deferring it while operations recover protects them.

Timeline for the Next Decision

Quarter 1: design development and baseline targets. Quarters 2 to 4: quarterly reports on both targets. Month 12: final decision on full scope, phased scope or further deferral.

Limits

Projections rest on assumptions about volume, payer mix and costs. Covenant terms vary. The bed tower's operating benefits are estimates.

Conclusion

The hospital can afford the tower on paper but not yet in practice. Deferring final approval for a year, while meeting two clear operating targets, protects the hospital's financial position and keeps the project alive.

5

References

Bai, G., & Anderson, G. F. (2016). A more detailed understanding of factors associated with hospital profitability. Health Affairs, 35(5), 889-897. https://doi.org/10.1377/hlthaff.2015.1193

Cleverley, W. O., & Cleverley, J. O. (2018). Essentials of health care finance (8th ed.). Jones & Bartlett Learning.

Pink, G. H., Holmes, G. M., D'Alpe, C., Strunk, L. A., McGee, P., & Slifkin, R. T. (2006). Financial indicators for critical access hospitals. The Journal of Rural Health, 22(3), 229-236. https://doi.org/10.1111/j.1748-0361.2006.00037.x

HA520 Unit 10 instructions, in plain terms

Unit 10 typically asks students to integrate the term's financial analyses into a comprehensive report for decision makers, often about a major investment. Instructions usually require an executive summary, historical performance, ratio analysis, risk factors, a pro forma or projection for the decision, options and a recommendation. Many instructors want the report written for a board or finance committee. Expect to cite finance texts and research in APA style, condense earlier analyses rather than repeating them, put composite numbers in brackets and keep the organization anonymous. Separating whether the organization can borrow from whether its operations can carry the result is often the central insight in this kind of report, and it should appear in the first paragraph.

How this HA520 Unit 10 example is built

The sample opens with a summary that gives the recommendation and its reason, with a margin note on putting the conclusion first. Three years of results and a ratio dashboard follow, citing research on financial indicators. A risk section cites research on hospital profitability, and the highlighted sentence contrasts covenant affordability with operating affordability. The pro forma shows coverage, cash and debt after borrowing, with a margin note. A section shows how the term's analyses fit together, then the tower's benefits, four options citing a finance text, two targets, management actions, board questions with a third note, community considerations, a timeline, limits and a conclusion. The summary fits on one page.

Where the points sit in the HA520 Unit 10 rubric

Comprehensive analysis rubrics in HA 520 usually award points for an executive summary, historical analysis, ratio interpretation, risk assessment, a pro forma, options, a recommendation, integration of earlier work and citations. Summary points depend on stating the recommendation first. Historical points go to clear trends. Ratio points reward interpretation against peers. Risk points require specific exposures. Pro forma points go to the decision's effect on coverage, liquidity and income. Option points require realistic alternatives. Recommendation points need conditions and targets. Integration points reward drawing on earlier analyses. Reports that anticipate board members' questions often earn the highest marks, since a finance committee will ask them whether or not the report does.

Common HA520 Unit 10 mistakes, and how to avoid them

Comprehensive reports often lose points by presenting every earlier analysis in full, burying the recommendation. Another gap is concluding that a project is affordable because covenants hold, without checking its effect on operating income. Some reports offer only approve or reject, ignoring deferral or phasing. Others set conditions without measurable targets. Put the recommendation first, condense history and ratios, name the risks, run a pro forma for coverage, cash, debt and income, compare options and set targets with dates. Then answer the questions board members are likely to ask, such as the cost of waiting, and set a date for the next decision.

Get an HA520 Unit 10 example written to your instructions

Whatever the Unit 10 case provides, several years of statements, a project proposal or analyses drafted over the term, belongs in the request alongside the rubric. One report joins it all to a single decision, pro forma and conditions included, delivered within 24-48h. First samples are free of charge. The paper above is an original model document written by our desk, not a submitted student paper and not an official Purdue University Global document.

More HA520 papers and MHA samples

HA520 Unit 10 questions, answered

Where can I find a free HA520 Unit 10 sample paper?

You can read the whole HA520 Unit 10 comprehensive financial analysis here, advising a composite hospital's finance committee on an $85 million bed tower, with three sources. Your own organization's decision can be analyzed the same way.

What is a pro forma in hospital finance?

A projection of financial statements and ratios showing the expected effect of a decision, such as borrowing for a project.

Why can a hospital afford to borrow but still not afford a project?

Covenants may hold while new depreciation, interest and operating costs erase operating income.

What targets might a board set before approving construction?

Measurable operating goals, such as a minimum operating margin and a maximum number of days in receivables, met over several quarters.

How long is the HA520 Unit 10 analysis?

Eight to ten pages addressed to the board finance committee, summary first.